| New Road and Bridge enables
access to construction site
of new commercial oil sands mining and processing facility

Steel girder erection, McKay Bridge
Canadian Natural Resources Ltd. (CNRL) is
constructing Horizon, a new commercial oil
sands mining and processing facility north of
Fort McMurray. Previously, the only access
to CNRL’s new Horizon mine site was
across the Athabasca River using an ice
bridge in the winter or by road through the
native hamlet of Fort McKay. To facilitate
mine access, CNRL required a new road
and bridge over the McKay River.
Following an intensive
evaluation process,
CNRL engaged the design/build team of
Kiewit Management Co. with Lead
Consultant Associated Engineering to
complete their first design/build contract for
the Horizon oil sands development. AMEC
Earth and Environmental and AMEC
Infrastructure Ltd. provided subconsultant
services to Associated Engineering.
The team’s mandate
was to design and
construct a safe, durable, cost-effective road
and bridge in an environmentally responsible
manner within a very short time period -
only ten months. CNRL required the road
and bridge to be designed and
constructed to Alberta Transportation
specifications. In addition, the bridge had to
accomodate 800 tonne over-load vehicles
and be wide enough to transport major
mining and process equipment to the site.

CNRL McKay River Bridge
By analysing the
comparative costs of
bridge length and resulting road earthworks,
the Team was able to produce a balanced
river crossing that met both budget and
schedule.
Bridge design had to consider the difficult
access to the site, due to the steepness of
the McKay River Valley and access restrictions
through Fort McKay. The design
allowed for bridge erection by conventional
crane lift or launching from the south
abutment, once the southern six kilometres
of road through boreal forest and muskeg
was complete.
Girders were designed in short, 21 metre
lengths to facilitate access to and manoeuvering
on site. Smaller girder lengths
enabled simple lifts from the riverbanks
without encroaching into the active McKay
River channel. The bridge span arrangement
enabled the piers to be located outside
the 1:100 year flood level on the McKay
River and therefore minimized environmental
impacts to the river.
“Due to the short construction period and
long lead-in time for manufacture and
delivery of plate girders, preliminary design
of the steel girders was fast-tracked so that
the steel could be ordered two days after
award of the contract,“ advised Project
Manager Robin Clee. “The bridge layout,
coupled with the flexible construction
approach significantly shortened the
construction schedule, thereby allowing the
project to be completed on time and within
budget.”
The bridge was opened for vehicle traffic
in
December 2003, successfully meeting the
tight schedule constraints. The total cost of
the project was approximately $18 million.
Other Associated Engineering personnel
involved in the project included John
Fussell, Julien Henley, Helen Du, David
Harvey, Alfred Kao, Steve Croxford, and James Nikolai. |