| City of Hamilton embarks
on a state-of-the-art Central
Composting Facility
The City of Hamilton, Ontario has begun
construction of a state-of-the-art Central
Composting Facility. Once constructed, the
facility will have the capacity to process
60,000 tonnes of organic household waste
per year. The $29.3 million facility, which
received $5.2 million in funding from the
Province of Ontario’s Provincial Millennium
Partnership Fund, is scheduled for completion
in the fall of 2006.
Several strategic goals identified
in the City’s
Solid Waste Management Plan led to the
design and construction of the Central
Composting Facility. The plan identified the
need to reduce waste sent to landfill. Like
many municipalities, Hamilton wanted to rely
less on its landfill and preserve the landfill’s
approved capacity and thus avoid finding
new landfill space or exporting the waste to
private facilities.
The City adopted a target of 65% waste
division
by 2008, which exceeds the Province of
Ontario’s target of 60% waste diversion. The
City estimates that 40% of its waste stream
consists of compostable organic material.
The organics will be collected separately at
curbside and delivered to the composting
facility for processing. The end product will
be marketed to public and private industry as
compost, fertilizer, or for other beneficial
uses.
Following an extensive procurement
process, the City selected the
Design/Build/Operate team of Maple
Reinders Constructors Ltd., Associated
Engineering, Aim Environmental, and
Christiaens Group. A partner on this team,
Associated Engineering is responsible for
approvals, design, and contract administration.
Aim Environmental is responsible for
operating the facility, and the Christiaens
Group is supplying the technology and
equipment for processing the compost.
The compost process
methodology is based
on the tunnel system, a proven, standardized
system operating throughout Europe and in
some areas in North America. The tunnel
system provides a controlled environment for
composting. All facets of the compost
process are controlled through a computerized
program model. The controlled environment
allows for a major reduction in the time
required to achieve high quality compost and
ensures the compost meets stringent government
end-product quality criteria.
Incoming organic waste will
pass through
screens and shredders and then travel by
conveyor to be loaded into 7 metre wide, 6
metre high, and 36 metre long concrete tunnels.
The compost is processed for seven to
ten days in one of ten Phase 1 tunnels, and
then transferred to one of six Phase 2 tunnels
for processing another seven to ten
days. The product is then conveyed to an
outside storage area for final curing and ultimate
exporting off-site.
Associated Engineering provided multi-disciplined
engineering services for the project,
completing the design on a very short schedule.
Project Manager, Chris Caers, advises,
“We worked closely with Maple Reinders and
the City to bring innovative design techniques
to this project.”
Associated Engineering staff involved in the
project include Chris Caers, Geoff Burn,
Mark Belanger, John Conlin, Simeon Dee,
George De Ridder, Paul Dufault, Patrick
Fritz, Dave Forgie, and Dale Harrison.
John Grylls retires after 35 years of service
Senior Electrical Engineer, John Grylls has
retired from Associated Engineering after 35
years with the company. John started his
working career with the National Coal Board
in the UK. In 1961, he decided to pursue a
degree in electrical engineering and was
accepted at the University of Wales. Upon
completing his degree in 1965,
John joined the English
Electric Atomic Power
Division. He later
returned to university to
obtain a Masters degree
in controls
engineering.
Seeking
adventure,
John and his
wife decided to
move to
Canada in the
late 1960s.
John joined
Associated Engineering’s Regina office in 1969 as an
Electrical Engineer. John took on a variety
of electrical design work on municipal and
industrial projects in Saskatchewan and
Alberta. In 1980, with a number of major
projects underway in Alberta, John moved to
the company’s Edmonton office.
Over the years, John
has worked on the
design of electrical systems for most of the
major water and wastewater works across
Canada, as well as many industrial facilities.
He has designed high voltage electrical
service, substation transformers, metering,
primary and secondary switchgear, motor
control centres, electrical distribution
systems, and lighting. Some of John’s major
projects include the Gold Bar Wastewater
Treatment Plant and E.L. Smith Water
Treatment Plant in Edmonton, the Nova
Chemicals project in Joffre, the Glenmore
and Bearspaw Water Treatment Plants in
Calgary, the Lulu Island Wastewater
Treatment Plant Expansion in the Vancouver
area, and the Mannheim Water Supply
Project in Ontario.
John is a member of the Institute of
Electrical and Electronic Engineers (IEEE),
Institution of Electrical Engineers (IEE), and
Instrumentation Society of America. He was
active in the local Edmonton chapter of
IEEE, serving as Chair as well as a key
organizer.
At his retirement reception held earlier this
year, colleagues, friends, and family
acknowledged John’s steadfast service to
Associated Engineering, his technical
strength, and valued mentorship to staff.
Staff across the company know John for his
good nature, his sense of humour, and his
sense of calm and optimism. Vice President
and General Manager, Rod Karius, remarks,
“John always made himself available to help
staff deal with technical challenges, not by
giving them the answer, but by showing them
how to approach the problem. He also took
a keen interest in the careers of our more
junior staff and, in doing so, was instrumental
in the development of our strong electrical
and controls capabilities.”
John served Associated Engineering
with
dedication. He was always ready and willing
to go to where the projects took him. We
could count on John to “get the job done”.
For this we thank John and his family.
In retirement, we wish John and his wife,
Reita, many years of health and happiness. |