| New high-rate process
resolves pre-treatment bottleneck at
the City of Red Deer WTP

Exterior view of Red Deer Water Treatment Plant No. 2
|
Implementing high-rate, ballasted
flocculation
at the City of Red Deer’s Water Treatment
Plant No. 2 has resolved capacity issues in
the plant’s pretreatment process. The
largest Actiflo installation in Western
Canada, the new pretreatment process has
doubled the plant’s pretreatment capacity in
half the footprint of the previous facility.
Faced with
increasing water demand from a
growing population as well as changes to
water quality standards, the City of Red
Deer retained Associated Engineering to
complete a Water Treatment Master Plan in
February 2001. The Plan provides the
framework for the City’s water treatment
needs for the foreseeable future.
Recently, the City entered
into agreements
to provide drinking water to communities
north of Red Deer by 2006. The demands
of the regional system required immediate
upgrades at the City of Red Deer’s Water
Treatment Plant No. 2. The City retained
Associated Engineering to design and oversee
construction of the recommended works.
The immediate concern
was the capacity
bottleneck in the plant’s pretreatment stage,
particularly during the spring. During spring
runoff, the Red Deer River, the plant’s water
source, tends to carry extra organic
materials as well as mud and silt stirred up
by increased water flow. During spring,
Water Treatment Plant No. 2’s existing solids
contact clarifiers were limited to a capacity of
43 million litres per day, compared to their
design capacity of 75 million litres per day.
After successful
pilot testing, two “Actiflo‚”
high-rate, ballasted flocculation/clarification
systems were selected for pretreatment
improvements. Actiflo‚ employs “microsand”
and polymer to assist fine particles in the
raw water to agglomerate, forming larger,
denser (“ballasted”) floc. The ballasted floc
settles quickly in lamella (inclined plate)
clarifiers, resulting in clarified water.

New Actiflo System at Red Deer WTP
|
The system’s
small footprint allowed the two
Actiflo systems to fit into one of the plant’s
two existing 20 metre by 20 metre solids
contact clarifiers. The clarification retrofit
doubles the pretreatment capacity.
The new pretreatment
system has continued
to operate and perform successfully since its
commissioning in May 2004. Upgrading the
pretreatment process has improved the
plant’s performance, reducing the previous
strain evident during spring runoff. Each
Actiflo train has consistently produced
clarified water well below 1.0 NTU, at
varying flows from 30 million litres per day to
60 million litres per day.
The Associated Engineering team
included
Barry Vallance (Project Manager and
Process Leader), Scott Witzke, Risco Protic,
and Corinne Wotton.
|