Innovative construction
tie-in detail ensures Lethbridge Water Treatment Plant
maintains production during UV installation

Ultraviolet Disinfection System
The City of Lethbridge operates a 150 million litre per
day water treatment plant, which supplies drinking water
to its 77,000 residents, as well as commercial, industrial,
institutional, and agricultural sectors. To address growing
concerns regarding drinking water quality, Alberta Environment
established more stringent standards, including 4 log (99.99%)
inactivation of Giardia, bacteria common in raw water supplies.
The City was faced with significant and expensive chemical
disinfection upgrades to meet this standard, and sought
a more economical solution.
The advent of ultraviolet (UV) disinfection for waterborne
cysts such as Giardia and Cryptosporidium offered such
a solution. Not only would UV allow the City to defer an
intermediate 3 log inactivation requirement, saving them
$500,000, but the City would also be able to reduce the
projected capital budget for 4 log inactivation from $20
million to $5 million.
The stringent regulatory deadline challenged the design
team of Associated Engineering, CH2M Hill, and the City
stakeholders to meet an aggressive implementation schedule.
To meet the deadline, the City decided to manage construction,
thus expediting implementation. This approach allowed the
City to start construction two months earlier than a conventional
design-bid-build project. Long delivery items were pre-ordered,
including the UV reactors, large diameter butterfly valves,
and magnetic flow meters.
The UV disinfection facility was designed for 150 million
litres per day to match the plant capacity. Five, 600 millimetre
diameter, Trojan UVSwift reactors with a capacity of 50
million litres per day each were installed to meet the
capacity, plus a minimum 50% redundancy requirement. Chemical
injection points for chlorine were installed upstream and
downstream of the reactors. Fluoride and ammonia injection
points were installed downstream of the reactors for induction
with a hydraulic mixer. As an added benefit, UV disinfection
allowed the City to maintain chloramination in the distribution
system, which was a consumer preference over free chlorination.
Ammonia used for chloramination had to be kept downstream
of the UV reactors due to potential interference with the
UV transmittance.
To maintain drinking water production, the City needed
to keep the water treatment plant clearwell on-line during
the construction tie-in. The City and the design team explored
a number of options for bypassing the clearwell during
construction, but none of these was deemed feasible.
The team developed an innovative tie-in detail that allowed
the plant to remain on-line during construction. The live
tie-in involved pre-drilling 50 millimetre diameter pilot
holes through the clearwell walls to guide divers from
the inside. Divers then attached 900 millimetre diameter “top
hats” over each pilot hole. These top hats were raised
blind flanges, gasketted around the edge and bolted to
the inside of the clearwell wall. Isolation valves on the
pilot holes were then opened to relieve the pressure behind
the top hats; the pressure from the water inside the clearwell
effectively sealed the top hats to the wall.

The top hats formed an annulus against the wall that allowed
a coring machine to drill a 750 millimetre diameter hole
from the outside into this annulus. Once the cores were
completed, the outlet and inlet piping headers to the clearwell
were installed, grouted in place, and a cast-in-place concrete
thrust structure was poured to hold the header in position.
The top hats were then removed from the inside of the clearwell.
Construction was completed and the plant commissioned
by December 2003, meeting the regulatory deadline. The
project, originally estimated at $5 million, was completed
$900,000 under budget.
Andy Barr, Project Manager for Associated Engineering,
states, “The success of the project was due to the
collaborative role that the City played with the design
team throughout design and construction.”
“The City of Lethbridge is very pleased with our
new facility,” reports Doug Kaupp, the City’s
Water Utility Manager. “It [the UV facility] has
operated flawlessly for the first year and has served to
reassure the community that our drinking water is of the
highest quality.”
Other Associated Engineering staff involved in the project
included Gord Roberts, Stella Tanner, Scott Witzke, Shane
Hemenway, the late Franz Bintoro, Sharon Schepicoff, and
Barry Vallance. |