|
New stormwater management works mitigate
flooding in southwest Calgary
Over the years, several neighbourhoods in southwest Calgary
have experience flooding during rainstorms. Remedial measures
implemented in the 1980’s and 1990’s provided
homeowners with some flooding relief. However, after a
major storm and resultant flooding in July 1996, the City
of Calgary decided to conduct
an updated analysis of the local stormwater management
systems. As a result of this analysis, the City
prioritized five flood remediation projects, and retained
Associated Engineering, together with subconsultants AMEC
Earth & Environmental and landscape architects, Lim
Associates, to complete design and
construction of these projects.
The objectives of this
project were to design and construct a dry pond and storm
sewer upgrades that would reduce the frequency of flooding
in the project area, considering impacts to local residents,
traffic, and overall project costs. During the preliminary
design phase of the project, the team developed a
computer model of the storm sewer system to fine-tune the
design of the storm sewer and dry pond. DDSWMM was used
to determine hydrologic flow rates for each catch basin
and XPSWMM was used to analyze the hydraulic capacities
of the proposed storm sewer system. QHM was used for continuous
rainfall simulations for the proposed detention pond, to
estimate how often and to what degree the pond would retain
stormwater during rainfall events.
The project team also
conducted an extensive constructability review of the 20,000
cubic metres dry pond and 4000 metres of storm sewer, which
ranged in size up to 1500 millimetres diameter. The challenge
was to determine the best alignment that minimized conflict
with existing infrastructure, mature trees, and a playground
in this well-established neighbourhood. The team also had
to find the best location for a 1500 millimetre diameter
section of the storm sewer to cross Crowchild Trail, a
six-lane urban arterial roadway.
“Retrofitting major
infrastructure improvements in an existing urban community
is not only technically challenging, but can have significant
impacts on the lives of residents as well,” advises
Project Manager, Dale Loewen. “We
held a public open house during detailed design to present
the proposed improvements to residents and to receive their
comments.” As a result of the public open house and
ongoing dialogue with community representatives, a number
of design modifications were made. For example, the design
of the detention pond was modified to include landscaping
improvements to an existing park and a new baseball diamond.
During
construction, the team, the City, and the Contractor worked
together to ensure that construction
minimized impact to residents’ daily lives and minimized
traffic impact. Work adjacent to two neighbourhood schools
was completed during the summer to avoid conflicts during
the school year. The open-cut crossing of Crowchild Trail
was planned well ahead of time with City of Calgary traffic
planning staff, and was completed in two stages in successive
weekends. Completed in 2004, the project met the City’s
objectives for flood relief, and provided improved park
space for the neighbourhood.
Other Associated Engineering
staff involved in the project included Duane Strayer,
Corinne Wotton, Sarah Huber, Tony Hasiuk, Scott Mills,
Dieter Foessel, Shane Hemenway, Harry Vandenberg, Justin
Fox, and Malcolm Cooper.
The design of the dry pond, completed
by AMEC, received an Award of Merit at the 2005 Consulting
Engineers of Alberta Showcase Awards. |