| Region of Halton’s
Oakville Water Purification Plant will provide improved
water quality

Project Manager, Elia Edwards
inspects installation
of Actiflo in
existing sedimentation tanks
|
A Construction is well underway for the $25 million upgrade
of the Regional Municipality of Halton’s Oakville
Water Purification Plant. The Oakville plant treats 120
million litres of Lake Ontario water daily. A conventional
water treatment plant, the facility employs coagulation,
flocculation, sedimentation, and dual-media filtration
with anthracite over sand for additional particulate removal.
The plant also uses a gas chlorination system to provide
zebra mussel control, taste and odour control, and primary
and secondary disinfection.
To improve the pre-treatment process and provide better
taste and odour control, the Region retained Associated
Engineering to provide engineering services for the plant
upgrade. The upgrade strategy included a retrofit design
and construction approach without expanding the existing
treatment and production capacities. The Region wanted
to stage construction activities to maintain overall plant
production above 50 percent during the low water demand
period, between September and April, and at 100 percent
during the high water demand period between May and August.
Associated Engineering’s retrofit design addressed
the various design criteria within the existing footprint
of the Oakville plant and considered the construction restrictions.
The plant upgrade includes:
- Improving the existing low-lift and high-lift pumping
stations
- Converting the existing two sedimentation basins into
two, parallel process trains comprising high-rate,
ballastedflocculation and ozonation
- Converting the existing three-staged tapered-flocculation
basins into multiple, self-contained chemical storage
areas for the chemical systems required by the new treatment
process
- Providing filter-to-waste
- Constructing a new, on-site treated water reservoir
- Converting the existing process wastewater treatment
system to a new gravity thickener system.
The pretreatment process will employ Actiflo®, a proprietary
process that uses microsand to “ballast” flocs,
and thus assist sedimentation. Pretreatment is followed
by intermediate ozonation for primary disinfection and
taste and odour control using liquid oxygen as the feed-gas
and a side-stream ozone injection system for mass transfer
of ozone into solution. The new chemical systems include:
- Calcium thiosulphate for chlorine and ozone residual
quenching
- Sulphuric acid for pH suppression
- Alum for pre-treatment
- Dry polymer for optimizing the pre-treatment strategy
- Hydrogen peroxide for advanced taste and odour control
- Sodium hydroxide for pH adjustment prior to distribution
- Fluoride for preventative dental care
- Chlorine for zebra mussel control, secondary disinfection,
and as a back-up primary disinfection strategy and
- Liquid polymer for optimization of the process wastewater
treatment system.
- The upgraded plant will provide improved water quality
and meet future water quality guidelines.
“Construction is proceeding well,” reports
resident inspector, Salma Dharsee. “The first phase
of upgrades, including a new treated water reservoir, gravity
thickener, Train 1 of the Actiflo® process, and ancillary
systems, will be commissioned in May 2006. The filter-towaste
upgrades and Train 1 ozone will be commissioned later in
2006. The remaining upgrades will be commissioned by June
2007.”
One key factor in facilitating this project was the partnering
between the Region, Associated Engineering, and King City
Group (the contractor). Ron Rae, Halton Region Project
Manager says, “The partnering atmosphere here is
very good. We’re working well with the consultant
and the contractor. Associated Engineering has been very
cooperative through the design and construction phase.
[They are] very open minded about the opinions of our staff.
They’re willing to embrace good ideas that haven’t
come from within their organization.” Rae adds that
this partnering attitude extends to the local area residents,
who have been involved in providing input to certain design
components throughout the design process. Rae explains
that it’s “part of the quality that we’re
going after for the citizens at home.”
Staff from across Associated Engineering have participated
in the project. Key Associated Engineering staff include
Elia Edwards (Project Manager), Fred Albanese (Construction
Project Manager), Mark Belanger, Derek Blakemore, Bill
Chisholm, Shane Cook, Iva Danilovic, Simeon Dee, Sam De
Rose, Salma Dharsee, Frank Dolling, Dusan Fil, Bill Harvey,
Jasna Halilovic, Dale Harrison, Jerry Helfrich, Vanja Jovic,
Austin Suriam, Caroline Korn, Alex Leong, Mike Liszega,
Charles McLeod, Amanda Odsen, Les Pickard, Rebecca Pringlemeir,
Tony Raposo, Paula Steel, Wendell Thiessen, Ian Wright,
and Joe Wyszomirski. |