Kelowna’s
new UV treatment improves water quality to customers
 |
Completed Poplar Point Water
Treatment Facilities |
The City of Kelowna’s new ultraviolet (UV) water
treatment facilities at its Poplar Point, Eldorado, and
Swick Road intakes on Okanagan Lake, are providing improved
drinking water to customers in north, central, and south
Kelowna. The $8 million project involved retrofitting
UV treatment into existing intake pump stations and chlorination
facilities while maintaining operation of the facilities
to ensure continued water supply to the City. With the
addition of UV reactors, the City's water utility is now
providing its customers with a two-stage disinfection
system consisting of UV primary disinfection followed
by chlorination.
The City’s water utility supplies water to more
than 50,000 residents and 1,700 industrial, commercial,
and institutional properties. The raw water source is
Okanagan Lake, with four intake locations. Previously
water treatment has been limited to chlorine disinfection.
However, in recent years concerns over water quality and
protozoa such as Giardia and Cryptosporidia have led the
City to seek enhancements to the primary disinfection
system at all intake locations.
The City engaged Associated Engineering to design the
upgrades. The City’s primary reason for selecting
Associated Engineering was our innovative approach, which
involved relocating the UV treatment equipment from the
discharge side to the suction side of the high lift pumps.
This approach reduced the risks associated with high operating
and transient pressures, and reduced any concerns associated
with UV lamp breakage.
The largest and most challenging of the three facilities
was the Poplar Point site, which is the City's primary
water supply and treatment facility. The Poplar Point
site consisted of two high lift pump stations and a chlorination
building located on a confined site immediately adjacent
to Okanagan Lake.
 |
UV system installation |
The scope of the new project
included providing increased intake capacity and increasing
the overall facility’s design capacity to 180 million
litres per day. The challenge for Associated Engineering's
design team was to find a way to integrate the UV treatment
facilities into this extremely constrained site while improving
suction side hydraulics to the high lift pumping system
and providing an opportunity for the City to add future
filtration. The ultimate solution was developed through
some innovative thinking by Associated Engineering’s
Sean Bolongaro and the City's Adrian Weaden. The solution
involved transferring existing high lift pumps from the
oldest high lift pump station to the newer facility. The
footprint of the old station was used to accommodate a
new intake connection, low lift pumps, and UV equipment.
A new interconnection structure was installed to tie the
new facilities to the existing intake pipe on the suction
side of the high lift pump station.
To address the City's energy efficiency objectives, the
design and contracting strategy included a number of energy
efficient design features including using lake water as
the building heating and cooling energy source.
 |
Sinking the new 1600 diameter
intake |
The project was scheduled to allow the components impacting
water delivery capacity to be constructed during the low
demand winter months, thereby ensuring that the City could
maintain full water supply throughout the construction
period.
To address the project's unique scheduling and operational
challenges, the implementation strategy involved a collaborative
effort involving the supplier, the installation contractor,
and the City. The City took on responsibilities for certain
construction components as well as programming and controls
integration. The supply of the UV equipment was tendered
and awarded to Calgon Carbon Corporation and novated into
the construction contract, which was awarded to Graham
Engineering and Construction Inc.
Construction began in January 2005. The transfer of pumping
equipment, demolition of the existing pump station, and
excavation and construction of the substructure for the
new UV Disinfection Facility were completed in the winter
2005. The 1600 millimetre diameter intake was floated
and sunk to a depth of 30 metres in May. Construction
of the new superstructure and installation of the low
lift pumps and UV equipment and associated electrical
and mechanical work was completed by year end. The City
then completed the programming and controls integration
to allow the new facilities to be commissioned in a staged
manner at the three sites in early 2006.
Bill Harvey, Associated Engineering's Project Manager,
stated, "The success of the project was due to the
hands-on involvement of the City in the design and construction
of the project." When asked about system performance
near the end of a several week hot spell, the City Project
Manager, Robin Barnes stated, "Despite having record
water demands, the new facilities met all supply and treatment
requirements. We have been pleased with the performance
of the overall system.”
Other Associated Engineering staff involved in the project
included Design Leader Sean Bolongaro, Miles Brook, Simeon
Dee, Mario Laurin, Peter Bakker, Sam Lui, and Brian Callow. |