Kelowna’s new UV treatment improves water quality to customers

Completed Poplar Point Water Treatment Facilities

The City of Kelowna’s new ultraviolet (UV) water treatment facilities at its Poplar Point, Eldorado, and Swick Road intakes on Okanagan Lake, are providing improved drinking water to customers in north, central, and south Kelowna. The $8 million project involved retrofitting UV treatment into existing intake pump stations and chlorination facilities while maintaining operation of the facilities to ensure continued water supply to the City. With the addition of UV reactors, the City's water utility is now providing its customers with a two-stage disinfection system consisting of UV primary disinfection followed by chlorination.

The City’s water utility supplies water to more than 50,000 residents and 1,700 industrial, commercial, and institutional properties. The raw water source is Okanagan Lake, with four intake locations. Previously water treatment has been limited to chlorine disinfection. However, in recent years concerns over water quality and protozoa such as Giardia and Cryptosporidia have led the City to seek enhancements to the primary disinfection system at all intake locations.

The City engaged Associated Engineering to design the upgrades. The City’s primary reason for selecting Associated Engineering was our innovative approach, which involved relocating the UV treatment equipment from the discharge side to the suction side of the high lift pumps. This approach reduced the risks associated with high operating and transient pressures, and reduced any concerns associated with UV lamp breakage.

The largest and most challenging of the three facilities was the Poplar Point site, which is the City's primary water supply and treatment facility. The Poplar Point site consisted of two high lift pump stations and a chlorination building located on a confined site immediately adjacent to Okanagan Lake.

UV system installation

The scope of the new project included providing increased intake capacity and increasing the overall facility’s design capacity to 180 million litres per day. The challenge for Associated Engineering's design team was to find a way to integrate the UV treatment facilities into this extremely constrained site while improving suction side hydraulics to the high lift pumping system and providing an opportunity for the City to add future filtration. The ultimate solution was developed through some innovative thinking by Associated Engineering’s Sean Bolongaro and the City's Adrian Weaden. The solution involved transferring existing high lift pumps from the oldest high lift pump station to the newer facility. The footprint of the old station was used to accommodate a new intake connection, low lift pumps, and UV equipment. A new interconnection structure was installed to tie the new facilities to the existing intake pipe on the suction side of the high lift pump station.

To address the City's energy efficiency objectives, the design and contracting strategy included a number of energy efficient design features including using lake water as the building heating and cooling energy source.

Sinking the new 1600 diameter intake

The project was scheduled to allow the components impacting water delivery capacity to be constructed during the low demand winter months, thereby ensuring that the City could maintain full water supply throughout the construction period.

To address the project's unique scheduling and operational challenges, the implementation strategy involved a collaborative effort involving the supplier, the installation contractor, and the City. The City took on responsibilities for certain construction components as well as programming and controls integration. The supply of the UV equipment was tendered and awarded to Calgon Carbon Corporation and novated into the construction contract, which was awarded to Graham Engineering and Construction Inc.

Construction began in January 2005. The transfer of pumping equipment, demolition of the existing pump station, and excavation and construction of the substructure for the new UV Disinfection Facility were completed in the winter 2005. The 1600 millimetre diameter intake was floated and sunk to a depth of 30 metres in May. Construction of the new superstructure and installation of the low lift pumps and UV equipment and associated electrical and mechanical work was completed by year end. The City then completed the programming and controls integration to allow the new facilities to be commissioned in a staged manner at the three sites in early 2006.

Bill Harvey, Associated Engineering's Project Manager, stated, "The success of the project was due to the hands-on involvement of the City in the design and construction of the project." When asked about system performance near the end of a several week hot spell, the City Project Manager, Robin Barnes stated, "Despite having record water demands, the new facilities met all supply and treatment requirements. We have been pleased with the performance of the overall system.”

Other Associated Engineering staff involved in the project included Design Leader Sean Bolongaro, Miles Brook, Simeon Dee, Mario Laurin, Peter Bakker, Sam Lui, and Brian Callow.


 In This Issue
  1. Little Mountain Reservoir project wins two awards from BC Ready-Mixed Concrete Association

    Saqib Khan helps rebuilding efforts in Pakistan

  2. City of Lethbridge University Drive improvements

  3. Sean Towers profile

  4. AMCL upgrades marine geophysics capabilities

  1. In-Service Traffic Safety Review for the City of Edmonton

    AE sponsors microbial fuel cell research

  2. Ed Bobick retires

    Associated Engineering raises $13,000 for cancer research

    Sheryl Stadnichuk takes home gold

  1. Toronto office moves to the East Mall

    Team AE ranks 7th in Edmonton Corporate Challenge

     
  2. Crouching Tiger, Hidden Master (Sam Lui)

    David Harvey receives fellowship from the Institute of Civil Engineers

     
  3. Employee News



 
Page:

AEToday Archive  |  Home