| New Okanagan compost facility
converts wastewater biosolids to Ogogrow™, a valuable
soil amendment

Sludge Receiving and Mix Buildings
under construction
|
The B.C. Okanagan cities of
Kelowna and Vernon have long taken leadership roles in
treating wastewater from their communities. Both cities
operate advanced wastewater treatment plants incorporating
biological nutrient removal (BNR) and create high quality
effluent. The BNR process removes phosphorus, a nutrient
found in wastewater that can lead to degradation of receiving
waters.
The Kelowna Wastewater Treatment Plant discharges effluent
to Okanagan Lake; the high quality of the effluent helps
to preserve the quality of the lake. Effluent from the
Vernon Water Reclamation Centre is stored during the winter
and, from late April to early October, used for irrigating
golf courses, orchards, a forestry centre, nursery, and
agricultural land.
Typically, plants similar in size to Kelowna and Vernon
use anaerobic (no oxygen) processes to stabilize their
sludge (biosolids). However, BNR plants do not typically
use anaerobic processes to stabilize sludge because bacteria
used in wastewater treatment to remove phosphorus can release
phosphorus under anaerobic conditions.
Since 1995, the City of Kelowna has composted sludge from
their wastewater treatment plant. The Kelowna biosolids
composting operation has been producing a product that
meets British Columbia’s Organic Matter Recycling
Regulation “Class A” requirements. Rich in
nutrients such as phosphorus, this product is trademarked
and marketed commercially as “Ogogrow”™,
a soil conditioner, for landscaping, orchards, gardens,
and potting soil.
Growing populations in both Kelowna and Vernon have driven
the need to expand the cities’ sludge stabilization
operations. The cities decided to collaborate on the design
and construction of a larger composting facility to meet
their joint needs.
Associated Engineering was selected to provide concept
development, pre-design, process selection, design, equipment
procurement, tendering, permit acquisition, construction
contract management, and post construction services for
the new composting facility.
The City of Kelowna decided to relocate the biosolids
composting operation to a parcel of land located south
of Vernon. The new biosolids composting facility had to
be designed to accommodate current and projected biosolids
production from the Kelowna, Vernon, Westbank, and District
of Lake Country’s wastewater treatment plants, and
from the Regional District of North Okanagan’s Septage
Facilities. In addition, operational criteria for the new
facility included the following:
- An aeration floor that could be easily loaded,
unloaded, and maintained
- No obstructions around the compost piles for
the front end loaders
- Automatic process control and data logging to
meet regulatory requirements
- Readily expandable to keep up with on-going
growth.

Aeration Equipment
|
“The City of Kelowna
had previously used the Aerated Static Pile (ASP) composting
process successfully,” reports Senior Environmental
Engineer, Dr. Dave Forgie. “So, the cities decided
to base the new composting facility’s process on
APS.” The advanced ASP process, provided by Engineered
Compost Systems (ECS), has positive and negative aeration,
enabling raw biosolids to be converted to Class A compost
in 80 days, compared to the conventional ASP process that
required a total of 120 days.
In addition to the composting area, the project also included
an administration building with office, laboratory, and
control room, sludge receiving and mix buildings, amendment
and processed material storage areas, and leachate and
surface runoff control and pumping. Stormwater and leachate
from the facility is collected in a detention pond. Solids
are removed and treated effluent is pumped to the City
of Vernon’s reclaimed water reservoir. Recycled effluent
is used as process water on site.
Project Engineer, Arash Masbough advises, “We decided
to separate the project into three construction contracts
and one equipment procurement contract. This allowed the
design to advance with construction activities.” The
project, from concept development to construction completion,
was delivered in 18 months. The facility capital cost of
$7.4 million was shared between Kelowna and Vernon, based
on existing biosolids production from each city. Maple
Reinders Inc. was the contractor for the main construction
contract.
Dick Vest led design and construction administration for
site works contracts. Gary Hussey provided project management
for the main construction contract.
The cities of Kelowna and Vernon recently received the
Union of British Columbia Municipalities (UBCM) Community
Award of Excellence in the Leadership and Innovation (Large
Community) category for this project. |