 |
CF-18 Hornet Fighter preparing for takeoff
|
Infrastructure upgrades at Canadian Forces Base Cold Lake accommodate future growth
Canadian Forces Base (CFB) Cold Lake is a tactical fighter training
base capable of deploying fighter aircraft at a moments notice to fulfill
the domestic and international roles of Canada’s Air Force.
In 1997, Defence Construction Canada (DCC) and the Department of
National Defence (DND) commissioned Associated Engineering to
carry out a comprehensive assessment of the Base’s existing roads,
sanitary, and storm collection systems. The assessment resulted in a
Master Infrastructure Condition Report and the design of a multiphase
upgrading program. The first phase of the upgrades were
implemented in 1999, which included eliminating the base sanitary lift
station and forcemain, and replacing them with a gravity trunk sewer
main. The remainder of the upgrades was delayed due to lack of
funding.
CFB 4 Wing Cold Lake are planning for growth due to construction of
new buildings and upgrading of existing facilities. To address this
future growth and the Base’s aging infrastructure, DCC/DND needed
to undertake a major upgrade of the existing facilities.
In 2007, Associated Engineering was commissioned to update the
1997 Master Infrastructure Condition Report, and all previously completed
detailed design phases. Two new infrastructure components, a
water distribution system and a communication system, were included
in the upgrade program.
The project will include:
1) Hydraulic assessment of the existing sanitary, storm, and water
systems
2) Detailed design of the proposed sanitary, storm, water, and road
systems upgrades and
implementation of the DND-provided Base
Communication System design, and
3) Assistance to Defence Construction Canada during the
construction and commissioning of the upgrades.
The project involves a number of design and construction challenges.
For example, the airplane hanger fire protection must be improved to
satisfy present Department of National Defence design standards.
These standards require the water distribution system to deliver 379
litres per second of water for 60 minutes. This will be achieved by
providing large diameter watermains to the hangers including a 3000
metre long, 500 millimetre diameter dedicated fire- line to the Tactical
Air Command (TAC) area, located southeast of the main portion of
the Base.
Base improvements will increase storm runoff volumes. However,
Alberta Environment has dictated that the upgraded storm sewer
system cannot exceed present discharge levels. To maintain present
discharge volumes, a 14,400 cubic metre storm surge facility is
proposed.
To produce an effective design of the upgrades, the existing underground
utility conditions must be known. This has proven to be
difficult due to limited record information. To identify specific utilities
and potential conflicts, a comprehensive hydrovac program was
undertaken to map the existing facilities in project areas.
Using new design standards means adopting steeper road/pipe
grades and pipe sizes/alignments. Detailed design of the upgrades is
difficult as most areas requiring rehabilitation are congested with
buildings and utilities.
Special design considerations needed to be taken into account to
ensure that the Base is able to fully function at all times during
construction. Project Manager Chris Skowronski advises, “The
biggest challenge will be during construction, as all utility services
will need to be maintained and construction impact on the Base
minimized. Special attention will be needed to maintain Base security
and minimize project impacts on daily Base activities and special
events, such as the international training exercise - Maple Flag.”
The construction of the proposed upgrades will be completed in six
phases over a planned seven year construction period. Chris says,
“Associated Engineering’s Gerald Ruta, E.I.T. (Infrastructure
Engineer) and Mario Gagnon, P.Eng. (Project Manager – Defence
Construction Canada) have left no stone unturned in the quest to
properly map the existing utilities. Their efforts will assist in the
improved design of the upgrades and elimination of potential
construction delays stemming from utility conflicts.”
|