 |
Buffalo Pound Lake |
New intake pump station and pipeline increases water supply to SaskWater customers
SaskWater owns and operates a regional
non-potable water supply system in the Belle
Plaine Industrial Corridor located between
Moose Jaw and Regina, Saskatchewan. The
existing system, comprising a 16.4 million litres
per day capacity pump station intake facility at
Buffalo Pound Lake and 20 kilometres of 400
millimetre steel pipeline, was originally
designed by Associated Engineering in 1991.
In 2007, Associated Engineering worked with
SaskWater to design and construct a booster
pump station to permit the system to operate at
maximum capacity. To address the significant
growth anticipated in the Belle Plaine Industrial Corridor in the next
three to five years, SaskWater has again commissioned Associated
Engineering to expand the existing non-potable supply system.
The expansion will include a new intake and pump station, and
18 kilometres of new 600 millimetres ductile iron pipeline.
The project, which is expected to be completed by August 2010, will
expand the existing operation by incorporating a new pump station
and lake intake complex at Buffalo Pound Lake beside the existing
pump station. The new pump station will have an initial pumping
capacity of 70.9 million litres per day and an intake capacity of 87.2
million litres per day. The pump station will operate in parallel with
the existing pump station with provisions for future expansion to
address the anticipated future water demand in the Belle Plaine
area, as well as to potentially replace the existing pumping station
completely.
Associated Engineering is leading the project as Prime Consultant,
and is responsible for the project management, preliminary and
detailed design, tender package preparation,
construction administration, and post-construc-
tion services. The schedule for the project is
aggressive in order to meet the requirements
of several industrial clients. To expedite the
regulatory approval process, Associated
Engineering’s project team invited representa-
tives from each regulatory agency to meet and
discuss issues they may have regarding the
project. As a result, many regulatory issues
were resolved prior to formal regulatory
submissions.
In addition, the project team looked at ways to
“fast-track” the construction schedule. Project Manager Peter Hooge
explains, “SaskWater was open to considering a construction
management approach which involves having the contractor as part
of the project team during the design process. Implementation of this
approach is expected to reduce the potential for constructability
issues which can occur in conventional design, tender, and construc-
tion project delivery methods and, most importantly, is expected to
shorten project timelines.”
The relatively shallow depth of the lake required design of an intake
screening system using fine mesh travelling fish screens and low lift
fish handling pumps.
The project is currently in detailed design with construction expected
to begin this summer. |