Associated Engineering's fast thinking and novel solution minimizes closure of overpass

Fully-restored Moody Street Overpass reopened to traffic
Fully-restored Moody Street Overpass reopened to traffic

On June 24, 2009, Associated Engineering was retained by the City of Port Moody, BC to assess damage to the Moody Street Overpass after a garbage truck, with its lifting arms elevated, accidentally hit the overpass, seriously damaging the superstructure. The overpass provides an important commuter corridor connecting the areas north of the CP Rail mainline with the remainder of the City, while businesses to the west use Murray Street, below, for access.

Closure of the overpass effectively cut off access to the west. Therefore the immediate priority was to secure the structure above Murray Street for controlled traffic use beneath the span. This required removing fractured superstructure concrete that was potentially hazardous, along with a rapid assessment of the safety of the damaged superstructure. Closure of the overpass forced a major detour onto many commuters, so the City was keen to reopen the structure as soon as possible. Our assessment was that the required structural repairs would take some time, but that following the immediate demolition phase, a one-lane detour plan across the east side of the deck was feasible with suitable traffic control.

Although serious damage was limited to only one girder, replacing the girder was a challenge. Dating from the 1970's, the 20 metre long precast girder was a type no longer produced in BC. Furthermore, the section was the central portion of three semi-continuous spans and was acting compositely with the concrete bridge deck. Replacing the damaged girder would therefore have required a considerable amount of deck to be removed which would have triggered an investigation into the safety of the partially-demolished bridge under traffic.

The truck had removed a large portion of the west fascia girder above Murray Street, near the north end of the ten-span structure.

Accident-damaged fascia girder
Accident-damaged fascia girder
 
Steel girder installation using fork-lift trucks
Steel girder installation using fork-lift trucks

Bridge reopened to traffic after only five weeks

When the Associated Engineering team of Shane Cook and David Chen examined the damaged girder, they determined that the original prestressing strands were mostly undamaged. However, with most of the concrete section fractured, they suspected that much of the prestressing force had been lost and would be very difficult to restore. Rapid analysis suggested that if the girder was repaired, it could safely carry its own weight without the intended prestressing force, but additional capacity for the superimposed loads would need to be added.

Shane and David devised a novel solution: adding a section of steel plate girder that could be rapidly procured and inserted alongside the fascia girder, but was slightly shorter in height to facilitate installation beneath the deck. The steel girder needed to project through the pier diaphragms into the adjacent spans to replicate the structurally continuous behaviour of the original design. To permit installation, the girder was designed in two sections with a bolted field-splice. Openings were sawn through the concrete diaphragms and the girder sections were shoehorned into place using fork-lift trucks, and bolted together. Bearing pads were placed at the piers caps and grouted.

While the girder was being fabricated, the fascia girder was repaired. Removing the damaged concrete did not result in strand pull-out, and so the straight strands were in the correct position and self-supporting. Additional reinforcing bars were selectively added to replace damaged stirrups and assist with crack control of the replacement concrete (which was non-prestressed). Selfcompacting concrete was used to fill the custom-built girder formwork.

Following installation, the steel girder was shimmed against the deck and preloaded by suspending weights near mid-span, followed by grouting of the gap between steel girder and bridge deck. The preloading ensured that the steel girder picked up its assigned portion of superstructure dead load, thereby relieving the fascia girder. After the steel girder was grouted, the pier diaphragms were reinstated. While the fascia girder will continue to undergo live load service deformations, any contribution to resisting imposed loading is unnecessary.

The critical construction work was carried out by West Shore Constructors, who coordinated a number of subcontractors and performed repairs. Shane Cook reports, "Thanks to fast and effective work all round, the Moody Street Overpass was opened to full two-way traffic operation on July 31 at 7 a.m."

 

In This Issue

  1. Dean Shiskowski appointed as
    Corporate Practice Leader,
    Wastewater Management


    Bermuda Airport project
    completed on time despite
    Hurricane Bertha

  2. ViewPoints: Complexities of water reclamation and reuse require holistic view

    Regional water systems are part
    of "Water for Life: Alberta's
    strategy for sustainability"
  1. Dean Reidt's philosophy: Give more than the minimum in work and in life

  2. Asset inventory and Waterworks System Assessments will help Northern Saskatchewan municipalities to develop comprehensive view of future financial needs of their assets

  3. Cold Lake upgrades will ensure the base can fulfill the domestic and international roles of Canada's Air Force

  4. Staff Appointments in BC

    Kelowna office takes on larger facilities

    Employee News
  1. Building Communities

    Burnaby office raises $532 for Big Brothers of Greater Vancouver

    AE Big Bike Riders raise over $7000 for Heart and Stroke Foundation

    Edmonton office "Canstruction" design/build team offers up giant Kraft dinner and raises $1,235 for the Food Bank

    Associated Engineering raises $21,986 for the Canadian Cancer Society

    Red Deer office raises almost $9,800 for the purchase of a new fetal heart monitor for the David Thompson Health Region


  2. Expansion of Milliken Reservoir and Pumping Station supports growth and enhances water supply for City of Toronto and Region of York
PAGE: 1 2 3 4 5 6 7 8 9 AEToday Archive Home