Awards 
 
 
Water & Environmental Awards
Infrastructure Awards


Consulting Engineers of Alberta
Showcase Awards

Annacis Island Wastewater Treatment
Plant Secondary Treatment

Little Mountain Reservoir Reconstruction

City of Saskatoon South East Sector
Stormwater Management Master
Plan

Canadian Consulting Engineers
2006 Schreyer Award for Goldbar
Wastewater Treatment Plant

Consulting Engineers of Alberta Award of
Merit

Rogers Sugar Ltd. - Taber Modernization
Project

Fulton Creek Regional Wetlands

Enhanced Water Quality Implementation

Wabamun Lake Level Mitigation and Water
Treatment Plant Project

Ratmalana-Moratuwa Wastewater
Collection, Treatment and Disposal
Feasibility Study, Sri Lanka

   
Transportation Awards


Canadian Consulting Engineering Award of Excellence - Sea to Sky Highway

Consulting Engineers of Saskatchewan -
Award for highway 9

iStructE Commendation for
Whitemud Creek Arch Bridge

Sea to Sky Highway Test Section

Highway 9, Yorkton, SK

Duke Point Underpass

Athabasca River Bridge

Vietnam National Highway No. 1A

Vancouver International Airport New
Parallel Runway

Deltaport Container Terminal

Esker Overhead

King George Flyover

Nass River Bridge

Associated Engineering wins 2006 Schreyer Award,
Canadian Consulting Engineering’s Highest Honour, for Gold Bar Wastewater Treatment Plant Industrial Water Reuse Facility Project

Associated Engineering received Canadian Consulting Engineering’s highest honour, the Schreyer Award, at the 2006 Annual Awards on October 26, 2006 in Ottawa, Ontario for our design of the Gold Bar Wastewater Treatment Plant Industrial Water Reuse Facility.

Working with the City of Edmonton and Petro-Canada, Associated Engineering developed a treatment process incorporating membrane filter technology to treat wastewater effluent from the City’s Gold Bar Wastewater Treatment Plant to the high quality that Petro-Canada required for use as process water at its Edmonton refinery. 

Associated Engineering completed detailed design and developed the construction strategy to retrofit the Gold Bar Industrial Water Reuse Facility into the wastewater treatment plant.  Compounding the complexity of the project, construction of the Industrial Water Reuse Facility had to be undertaken without impacting plant operations at the Gold Bar plant, which treats wastewater from 700,000 residents as well as industrial and commercial clients.  Design and construction also had to consider other ongoing construction at the Gold Bar plant. 

Start up and commissioning of the $14 million Gold Bar Industrial Water Reuse Facility--the largest water reuse facility to employ membrane technology in Canada--was completed on budget and on schedule in December 2005, without impacting plant operations or adjacent construction.  

Transmission of 5 million litres per day of recycled water to Petro-Canada began in May 2006.  Ultimately, the facility will be capable of producing 40 million litres per day of water. 

In addition to supplying water to Petro-Canada, the Gold Bar Water Reuse Facility will also supply recycled water to Edmonton’s Parks and Recreation Department to service a nearby park and ski hill as well as to the neighbouring Strathcona County.  The Gold Bar Industrial Water Reuse Facility recycles a valuable water resource for reuse, and protects the water quality, aquatic life, and aquatic habitat in the North Saskatchewan River by reducing the wastewater effluent discharge to the river.

Associated Engineering wins Commendation Award from IStructE

Associated Engineering received a Commendation Award in the pedestrian bridge category from the Institution of Structural Engineers (IStructE) for the design of the Whitemud Creek Arch Bridge in Edmonton.

The IStructE Structural Awards are the world's preeminent awards for structural engineering excellence. The annual international awards celebrate excellence in structural engineering.

See http://www.istructe.org/structuralawards/ for more information on the IStructE awards.

Associated Engineering receives three awards at the
Consulting Engineers of Alberta Showcase Awards

At the CEA's Showcase Awards on February 3, 2006, we received an Award of Excellence in the Community Outreach, In-House Initiatives category for our in-house Wellness Program. We also received an Award of Excellence in the Natural Resources, Mining, Industrial category and Award of Merit in the Environmental category for the Gold Bar Wastewater Treatment Plant Industrial Water Reuse project.

Associated Engineering wins Canadian Consulting Engineering
Awards of Excellence

Associated Engineering’s design of the Sea to Sky Highway Test Section received an Award of Excellence at the annual Canadian Consulting Engineering Awards of Excellence in November 2005. Our design of the test section is part of the B.C. Ministry of Transportation’s upgrade of the Sea to Sky Highway from Vancouver to Whistler for the 2010 Olympics. See article in AE Today  http://www.ae.ca/aetoday/050302.html for more information

Consulting Engineers of Saskatchewan present
Awards to Associated Engineering for Highway No. 9 in Saskatchewan

Associated Engineering recently received Awards of Excellence for Technology Innovation and Infrastructure from the Consulting Engineers of Saskatchewan for our work on Highway No. 9 Improvements in the City of Yorkton.  See article in AE Today http://www.ae.ca/aetoday/050303.html for more information


Association of Consulting Engineers of Canada and Canadian Consulting Engineers magazine Award of Excellence1999 Consulting Engineers of B.C. Award of Merit

Annacis Island Wastewater Treatment Plant Secondary Treatment Upgrade, Delta, B.C.
Greater Vancouver Regional District

Until October 1998, the Annacis Island Wastewater Treatment Plant discharged primary-treated wastewater from one million people to the Fraser River, the world's largest salmon fishery. To protect this valuable resource, the Greater Vancouver Regional District has completed an upgrade of the Annacis Island plant to secondary treatment. The largest and most technically-advanced wastewater treatment facility of its kind in the world, this plant incorporates many innovative and complex features including:

  • The world's first extended thermophilic anaerobic digestion process which produces almost pathogen-free biosolids
  • One of North America's first sludge screen installations
  • One of North America's first biofilter installations for odour control
  • A raft foundation which ties the large tank and building foundations together to eliminate the risk of tank separation and minimize differential settlement during a liquefaction event
  • The world's largest vertical turbine solids handling pumps
  • A state-of-the-art computer data acquisition and control system that communicates with more than 5000 pieces of equipment throughout the site.
To conserve energy, the plant uses biogas generated by sludge digestion to provide approximately 50% of the plant power demand and emergency power during service interruptions. In addition, waste heat from the cogeneration engines is recovered for heating.

Completion of this project met all critical milestones, with costs almost $90 million below the original $530 million budget. Since start-up, the Annacis Island plant has consistently met stringent provincial discharge criteria. This improvement in effluent preserves the Fraser River's fisheries resource and marine environment, provides additional safeguards to public health, and maintains water-related recreational values.



Consulting Engineers of BC Award of Excellence

Little Mountain Reservoir Reconstruction, Vancouver, B.C.
Greater Vancouver Regional District

The Consulting Engineers of B.C. (CEBC) recently presented Associated Engineering and Sandwell Engineering with an Award of Excellence for the Little Mountain Reservoir Reconstruction Project in Vancouver, B.C. Sandwell, as the prime consultant, with Associated Engineering as the main subconsultant, led a comprehensive team to carry out the detailed design and construction management of the 138 million litre Little Mountain Reservoir, located in Vancouver’s Queen Elizabeth Park. Sustainability principles were drivers throughout the project, including maximizing recycling of demolished materials and use of EcoSmartTM concrete. The project also received the Professional Engineers and Geoscientists of B.C.’s 2003 Sustainability Award.




Consulting Engineers of Saskatchewan
Award Excellence


City of Saskatoon South East Sector Stormwater Management Master Plan

CES awarded the Brian Eckel Award of Excellence in the Environmental Category to Associated Engineering for the South East Sector Stormwater Management Master Plan for the City of Saskatoon.

Saskatoon's South East sector is under pressure for both development and conservation. The purpose of the stormwater management master plan was to determine how best to develop the area, while minimizing impact on the stormwater management system and considering land development, habitat preservation, and recreational opportunities. Associated Engineering developed three sustainable concepts, considering natural resources, wetlands, habitat, geotechnical conditions, hydrotechnical and hydraulic constraints, modelling, stormwater quality, and the existing stormwater system. The project featured extensive stakeholder and public involvement to determine issues and build consensus.





Consulting Engineers of Alberta Award of Merit

Double Barrel Pipe Repair and Replacement, Edmonton, Alberta
City of Edmonton

The Consulting Engineers of Alberta recently presented Associated Engineering with an Award of Merit for Edmonton’s Double Barrel Pipe Repair and Replacement Project. Associated Engineering designed a pilot test and subsequently completed design and construction administration for relining double-barrel pipes which handled sanitary and storm flows. The dividing wall between the double-barrel pipes had deteriorated over time, which resulted in sanitary sewage leaking into the storm side of the pipe, and ultimately, into the North Saskatchewan River. Design incorporated relining using cast-in-place-pipe (CIPP) technology, and maintained the structural integrity of the dividing wall and accommodated cold weather construction. In presenting the award, judges commented that, "This project incorporated basic principals and innovations in resolving a very unique problem. This project demonstrates truly creative engineering at its best."



Consulting Engineers of Alberta Award of Excellence - Resource Development and Award of Merit - Environmental Category


Rogers Sugar Ltd. - Taber Modernization Project, Taber, Alberta
Rogers Sugar Ltd.

Rogers Sugar Ltd., a major sugar producer in Canada, recently invested in the modernization of their Taber, Alberta facility. The Taber Modernization Project was undertaken over a two-year period to increase the production of the sugar beet processing factory to 6,000 tonnes of beets per day, a 50% increase. Rogers Sugar retained Associated Engineering for engineering, procurement and construction management of the modernization work, including an $8.5 million wastewater treatment plant that was designed, constructed and commissioned in less than one year.

In presenting the Award of Excellence - Resource Development and Award of Merit - Environment to Associated Engineering, judges noted that, "The Rogers Sugar Ltd. project illustrates a good combination of technical excellence and a good use of technology which benefitted both the company and the community....[The project] was delivered in a short time frame, utilized international collaboration and products, tried to advance a technology in a previously untried market (food industry), reduced the environmental impact on the city's infrastructure, and led to a 50% increase in production."



Consulting Engineers of Alberta Award of Excellence


Fulton Creek Regional Wetlands, Edmonton, Alberta
City of Edmonton

Associated Engineering had identified a need for a stormwater management pond along Fulton Creek as part of the 1994 Drainage Master Plan for this future residential area. Due to economic constraints, the City of Edmonton did not immediately proceed with construction of the stormwater management pond. In 1996, during the design of the extension of Whitemud Drive, a four-lane freeway, Associated Engineering recognized the opportunity to economically construct the Fulton Creek stormwater management facility by excavating the large quantity of fill required to construct the freeway embankment from the Fulton Creek area. From this excavated area, Associated Engineering designed the Fulton Creek Wetlands.

The wetlands create a naturalized area for waterfowl nesting, birds, and wildlife, serve as a regional recreational and wildlife viewing area, improve the quality of stormwater runoff, and reduce the risk of downstream flooding. Judges for the award said, "The Fulton Creek project] goes beyond simply providing an engineered solution to the problems at hand, it instead provides an environmentally conscious engineered solution which contributes to the project but also to the community in a significantly larger number of ways than other solutions might have done."

Project sheet


Consulting Engineers of Alberta Award of Merit

Enhanced Water Quality Implementation, Taber, Alberta
Town of Taber

When the Town of Taber needed to improve water quality from their water treatment plant, they retained Associated Engineering to come up with modifications. After successful completion of a pilot testing program, Associated Engineering recommended a dissolved air flotation (DAF) addition to the plant to improve particle removal.

The new 28 million litre per day DAF clarification system is by far the largest in Western Canada and is the first system to be designed and built in place. The fully-automated plant now produces clearer, better tasting water, and increases public health protection by improving Giardia and Cryptosporidium removal and reducing disinfection byproducts. Moreover, the process has decreased chemical usage and wastewater production at the plant by 50% and 75%, respectively.



Canadian Consulting Engineers Award of Excellence and Consulting Engineers of B.C. Lieutenant Governor’s Award of Excellence

Sea to Sky Highway Test Section, B.C.
Ministry of Transportation

The design of the test section is part of the B.C. Ministry of Transportation’s upgrade of the Sea to Sky Highway from Vancouver to Whistler for the 2010 Olympics. The existing highway is characterized by sharp curves, steep climbs, and dramatic drop-offs to the ocean below. The Ministry wished to upgrade the highway to improve safety, reliability, and capacity for travelers. The Ministry selected Associated Engineering with Golder Associates to complete detailed design of an 800 metre long test section north of Horseshoe Bay. The objectives of the test section were to demonstrate that the challenging construction of the entire highway could be done on time, economically, and without major traffic closures.

Specific challenges along the test section included near vertical rock cuts, marginally stable rockfill slopes, and the nearby CN Rail corridor. The design team addressed the constraints by developing unique downslope structures (half bridges) and innovative retaining wall systems. The project was delivered on schedule, 30 percent under budget, and requiring only short (20 minute), single-lane road closures.


Consulting Engineers of Saskatchewan Awards of Excellence for Technology Innovation and Infrastructure

Highway No. 9, Yorkton, Saskatchewan
City of Yorkton & Saskatchewan Department of Highways

The provincial highways located through Yorkton are major routes for moving people and goods in Saskatchewan and across Western Canada. Highway No. 9 from Queen Street to Darlington Street is an important part of the roadway network. Located within this section is the intersection of Broadway Street (Highway No. 10), the busiest intersection in the City, serving over 10,000 vehicles per day. The increase in truck traffic and weights, poor soil conditions, and poor surface drainage contributed to severe deterioration of the existing roadway surface, resulting in extreme cracking and poor ride.

The City of Yorkton formed a partnership agreement with Saskatchewan Highways and Transportation to complete improvements to Highway No. 9. The Partnership engaged Associated Engineering to complete the survey, functional and detailed design, tendering, and construction inspection and administration, and provide overall project management.  Associated Engineering completed the design using CAiCE design software to create a digital terrain model and develop cross-section design templates, horizontal alignment, vertical profile, automated superelevation, and two-dimensional and three-dimensional visualization.  The team completed off-tracking analysis for every turning movement using AutoTurn 4.0 vehicle off tracking simulation software. This software allows the designer to simulate the turning movements of large tractor- trailer units, thus optimizing the surface area required at each radius.  The project stakeout was completed using total station and real time kinematic (RTK) GPS survey methods. This method allowed for electronic transfer of design data and field stakeout with sub-centimetre accuracy at significantly reduced cost.

Highway No. 9 was completed in October 2005, improving the transportation corridor and providing economic and social benefits for the City of Yorkton and Province of Saskatchewan.


Precast/Prestressed Concrete Institute Special Recognition Award:

Duke Point Underpass, Nanaimo, B.C.
B.C. Ministry of Transportation and Highways

Duke PointThe Duke Point Underpass in Nanaimo is one of many bridges on the $1 billion Vancouver Island Highway project. The Ministry of Transportation and Highways originally tendered the bridge as two, twin-cell, cast-in-place, post-tensioned, trapezoidal box girders. Each girder was 1500 mm deep, connected by a cast-in-place concrete deck slab with edge cantilevers. Spans required were 21 m, 38 m, and 21 m, with a 17.5 m wide deck. The superstructure was skewed, curved-in-plan and super-elevated.

The design required construction on falsework, and provision for future external post-tensioning. The contractor, Emil Anderson Construction Ltd., wished to condense the construction schedule, and eliminate most of the falsework for construction of the superstructure. The Ministry's contract documents allowed for provision of alternative solutions, as long as the alternate design was of similar depth and span configuration, and aesthetically pleasing.

Associated Engineering proposed a precast concrete bridge, with similar span, geometry, and aesthetics. The innovative concept utilized an available, precast trapezoidal box girder form to manufacture segments which were post-tensioned together in the field. The precast girders allowed the Contractor to minimize falsework. Precasting concrete manufacturing paralleled substructure construction, thereby shortening the construction schedule.

To simplify construction, the concept avoided the use of external diaphragms except at the abutments. Here, integral ballast walls provided torque-restraint for the girders and a location for the post-tensioning anchorages. Use of monolithic abutment walls also eliminated the cost and maintenance associated with expansion joints at deck ends. Additional savings were achieved by adding the future post-tensioning provision to the initial prestressing provided during construction.

The Ministry accepted Associated Engineering's alternative design, which was priced at about 20% less than the original cast-in-place design. This project demonstrated that efficiently designed, elegant precast concrete solutions can be highly cost-effective when compared with equivalent cast-in-place designs.

Project sheet


Consulting Engineers of Alberta Award of Excellence for Resource Development and Consulting Engineers of Alberta Award of Merit for Value Engineering/Risk Management:

Athabasca River Bridge, Alberta
Suncor Inc. - Oil Sands Group

Suncor BridgeSuncor's Athabasca River bridge crosses the Athabasca River approximately 30 km north of the Fort McMurray providing access to Suncor's new Steepbank tarsand mine. Approximately 400 m long and is 22.5 m wide, the bridge carries two traffic lanes and 12 production pipelines for hydrotransport of tarsand and tailing sand return.

Associated Engineering selected a unique foundation system consisting of 2.5 m diameter rock socketed piles to reduce cost, risk, and the environmental impact associated with cofferdams during construction. The rock characteristics were carefully addressed at each pile location through a series of boreholes and an appropriate tip elevation chosen. The piles are connected with a concrete diaphragm above river level. The controlling load for the bridge substructure is that associated with ice impact during the spring break-up. Ice forces that impact on one pier are transferred through the bearings to the deck and hence are shared by other substructure elements including the abutments. This leads to a structural concept that has a high level of "toughness".

The superstructure for the five-span bridge consists of continuous 3.3 m deep steel plate girders with a reinforced concrete deck varying in thickness from 300 mm to 450 mm. The bridge is designed to carry unloaded mine haul trucks with a gross vehicle weight of 170 tonnes on two axles approximately five times higher than a standard highway design axle loading.

The bridge was constructed under a $25 million fast-track, design-build contract with Kiewit Management Ltd, and opened to traffic in the fall of 1997.

In winning the Consulting Engineers of Alberta Showcase Awards, the judges noted "the short design/build period which allowed the client to gain almost two years on its development plan, its utilization of the adverse winter environment as an advantage during pier construction, numerous unique design features, and innovative approaches to geotechnical challenges".

Project sheet


Consulting Engineers of Alberta Award

Wabamun Lake Level Mitigation and Water Treatment Plant Project, Wabamun Lake, Alberta
TransAlta Utilities Corporation

Wabamun Lake, located 60 km east of Edmonton in central Alberta, supports sport and commercial fisheries and sees extensive year-round recreational use. Lower than normal lake levels have resulted from below average precipitation in recent years and the impact of TransAlta Utilities' operation of three electrical generating plants in the area. To offset the impact of their operations on the lake level, TransAlta established a mitigation plan which involves taking water from the North Saskatchewan River, and cooling and treating the water before transferring it to Wabamun Lake. To minimize the potential for introduction of non-indigenous biota into the lake, TransAlta required a state-of-the-art water treatment facility.

TransAlta Utilities Corporation retained Associated Engineering to provide engineering, procurement and construction management for the water treatment plant. Camp Dresser & McKee provided ozone process technical review services.

The water treatment facility will use both physical and chemical barriers to prevent the transport and survival of organisms from the source water to the receiving water, and produce a quality that complies with the latest edition of the Guidelines for Canadian Drinking Water Quality. The water treatment facility was designed to meet or exceed U.S. Environmental Protection Agency (EPA) Surface Water Treatment Rule (SWTR) standards for removal or inactivation of bacteria, parasites and viruses. Water quality objectives are turbidity less than or equal to 0.5 NTU, 5.5 log inactivation of Giardia oocysts, and 4.0 LOG inactivation of viruses.

Key processes of the 45 ML/d facility are raw water pumping, a 36 m diameter solids contact upflow clarifier, six dual-media filters, ozone disinfection system, a four-cell cooling tower, and a treated-water effluent system. The plant's ability to achieve 5.5 log inactivation of Giardia oocysts makes it a Canadian first. The multiple barrier treatment process utilizes ozone disinfection to accomplish the major portion of this inactivation. Cooling towers keep the transferred water temperature within 3%C of lake water temperature, minimizing any temperature impacts on the lake.

Water treated by the new facility was first discharged to Wabamun Lake on September 26, 1997, 21 months after the start of preliminary design.

Project sheet


Consulting Engineers of B.C. Award of Merit:

National Highway No. 1A
Government of Vietnam, Ministry of Transport

National HighwayOver 1,600 km in length, Vietnam's National Highway No. 1A is the country's main transportation corridor. Highway No. 1A extends from the Chinese border in the north (near Hanoi, the capital city), to the southern tip (near Ho Chi Minh City, formerly known as Saigon). As part of Vietnam's urgently-needed transportation infrastructure development and renewal, Vietnam's Ministry of Transport designated thirty-six (36) bridges along Highway No. 1A for immediate replacement.

With loans from the Japanese Overseas Economic Cooperation Fund, the Ministry retained an international engineering consortium to perform the planning, detailed design and contract document preparation, working together with local Vietnamese engineers and technicians. This consortium, led by the Japanese engineering firms Pacific Consultants International and Nippon-Koei Co. Ltd., included the joint venture team of Klohn-Crippen Consultants Ltd. and Associated Engineering International Ltd.

This engineering team was responsible for technology transfer, supervision of bridge design and construction planning for the Vietnamese engineers, who were unfamiliar with international design standards and preparation of drawings and specifications for international tendering. As well, there were language difficulties that had to be overcome. Complicating the process further was the tight deadline for this project. The Ministry required that all 36 new bridge designs had to be ready for construction tendering (with prequalified international construction joint ventures) in only nine months time.

Through careful discussions, meetings and training sessions with state-of-the-art computerized design technology, our team produced a streamlined design procedure to standardize and optimize designs and drawing production. The process was very successful, enabling all 36 bridge designs to go to construction tender as per the Ministry's schedule.





Consulting Engineers of B.C. Award of Merit:


New Parallel Runway, Richmond, B.C.
Vancouver International Airport Authority

New runwayThe Vancouver International Airport Authority (YVRAA) has undertaken a program to improve and expand airport operations to better serve the community's and the province's needs and development priorities. To this end, YVRAA retained Crippen Associated Consultants, a joint venture of the Crippen Division of H.A. Simons Ltd. and Associated Engineering, to prepare project definition reports and cost estimates for site development works. Subsequently, Crippen Associated Consultants was engaged to prepare detailed design drawings, technical specifications and provide resident engineering services during construction of the new parallel runway, new taxiways, airfield lighting system, civil works, and associated ground-side works.

The project team dealt effectively with the sensitive geotechnical and environmental concerns of the site and offered innovative solutions, such as a system to protect existing utilities and a materials management plan, which reduced overall project costs.

The new Parallel Runway will increase the ultimate airport capacity by 40% and accommodate all current types of aircraft, as well as the anticipated aircraft of the future. The Runway features a Category III Lighting System, the first of its kind in Canada. The airfield lighting system will maximize use of the airport by allowing aircraft operation to continue at visibility limits down to 200 m.

At 9:30 am on Monday, November 4, 1996 the world's newest large airliner, the Boeing 777-200, became the first aircraft to land on the new Parallel Runway. This marked the successful conclusion of this $95 million project on schedule and within budget.

Project sheet


Consulting Engineers of B.C. Award of Merit:

Deltaport Container Terminal, Roberts Bank, B.C.
Vancouver Port Corporation

DeltaportDeltaport is a 40 hectare container terminal at Roberts Bank with a construction value in the order of $50 million. It is the major component in the Vancouver Port Corporation's initiative to maintain and improve Vancouver's share of the west coast container trade. A terminal design which provided efficiency in container handling was considered essential to the productivity and overall success of the Deltaport facility.

Acting as a subconsultant to Klohn-Crippen Consultants Ltd., Associated Engineering provided specialist design input in the area of civil engineering for this important development project, most particularly related to grading, paving and surface drainage. Associated Engineering was responsible for preliminary design, detail design and construction inspection of surface works for the entire site which included a container yard, intermodal yard, gate area, access causeway, internal roads and parking areas.

Special surfacing design features for this facility include a uni-directional grading scheme with slot drains, tailored to rubber tired gantry and top pick operations, reinforced concrete runways for rubber tired gantry operations integrated with slot drain crossings, and areas of roller compacted concrete pavement as well as asphalt on granular pavement.




Consulting Engineers of B.C. Award of Merit and 1995 Canadian International Development Agency (CIDA) Canadian Award for International Development:

Ratmalana - Moratuwa Wastewater Collection, Treatment and Disposal Feasibility Study
Metropolitan Environmental Improvement Program
Government of Sri Lanka

RatmalanaThe Ratmalana - Moratuwa area, located south of Colombo, developed as an industrial/residential suburb of Colombo in the 1950's. Approximately 350,000 inhabitants live within the Region. The area is characterized by mixed land uses with a large number of industrial and institutional facilities intermixed with residential and commercial areas. Industrial pollution has long been recognized as a problem in the area with liquid wastes from industries being discharged untreated into nearby drainage courses. The domestic wastewater is directed to individual septic tanks. Pressure from an expanding population has forced residents to construct wells adjacent to existing septic tanks, in violation of minimum safe distances required by planning agencies. A high water table further aggravates this problem and faecal contamination of wells is common.

The Government of Sri Lanka, through the Metropolitan Environmental Improvement Program engaged the services of Associated Engineering to undertake a wastewater management study for the Ratmalana - Moratuwa Area. The objective of the study was to assess the potential for waste minimization, pollution prevention, and a central wastewater collection, treatment and disposal system for the area. The project involved assessing wastewater management scenarios available to the area and further developing the preferred scenario. This included estimating and computer modelling sewerage flows for the conceptual design of the collection system, the central treatment plant, and an ocean outfall. The study also included establishing industrial pretreatment standards, reviewing viable ownership and management options, conducting financial analysis of the long term viability of the system, developing an implementation plan, and assessing potential environmental and social impacts of the project on the surrounding areas and residents.

The Canadian International Development Agency and the World Bank provided funding for the $600,000 study.

Project sheet


Consulting Engineers of B.C. Award of Merit

Alberni Pulp Mill Pipeline Trestle Replacement
Macmillian Bloedel Ltd.

Associated Engineering provided preliminary and detailed design services to replace 700 m of a deteriorated timber trestle located in an ecologically-sensitive tidal flat. The trestle supports a 1370 mm water pipeline which supplies MacMillan Bloedel's Alberni Pulp and Paper mill with process water. The project had to be completed without disruption to important fish habitat while maintaining a continuous supply of water to the mill.

Associated Engineering worked with the owner to develop an innovative solution which included the construction of a pile-supported working platform above the pipeline. The platform permitted demolition of the existing trestle and construction of the new trestle without disruption to the environmentally-sensitive fish habitat or interruption of the mill's water supply.




Precast/Prestressed Concrete Institute Award and Harry H. Edwards Industry Advancement Award:

Esker Overhead, near Terrace, B.C.
Ministry of Transportation and Highways

Esker OverheadThe 50 m-span Esker Overhead is located on Highway 16 between Terrace and Prince Rupert, B.C. Some 1500 km by road from the Vancouver area, the remote location offered a considerable challenge to design economically using structural concrete.

The structure provides grade separation for a previously at-grade crossing of the Canadian National Railway, and allows for the existing plus a future operational track. Site constraints mandated a crossing at a 60% skew. During detailed design by the project consultant, the bridge skew was reduced to 45%, and reinforced earth curved-in-plan abutments were selected. Designs in precast concrete and structural steel were offered for tender with alternate designs using segmental precast girders permitted under the contract.

During the tender period, it became apparent that the one-piece precast girders were very costly to transport (either by barge to Prince Rupert or by rail) to the site and to erect using two large cranes. Con-Force Structures Ltd. commissioned Associated Engineering to prepare an alternate segmental design. This option permitted segment transportation by truck and erection by a single crane. The segments were erected on falsework and field post-tensioned together prior to placement of the concrete deck. The post-tensioning anchorages were located in the cast-in-place end diaphragms and segment splices were field-grouted after splicing post-tensioning ducts. The innovative concepts used resulted in a cost saving of $140,000 compared to the steel alternative.

The bridge won the 1991 Precast/Prestressed Concrete Institute of Chicago Award for Bridges of greater than 41 m span and the prestigious Harry H. Edwards Industry Advancement Award. The jury cited the technical innovation which permitted a precast concrete solution to be produced economically in a situation where it would not normally be applicable.





Consulting Engineers of B.C. Award of Merit:

Nass River Bridge
B.C. Ministry of Forests

Nass River BridgeIn order to provide access to new unlogged watersheds on the west bank of the Nass River in northwestern British Columbia, the Ministry of Forests needed a new bridge crossing of the Nass Canyon. A cable-stayed bridge with a 96 m main span with timber deck was offered for tender. The lowest tender received was for over $2.3 million which exceeded the Ministry's budget.

Associated Engineering designed an alternate steel-box girder design with precast concrete deck which was tendered at $1.4 million by a leading bridge contractor. The alternate 108 m-long bridge provided equal or better quality, was within budget and was accepted by the Ministry for construction. The 96 m main span was installed by launching and is believed to be the longest span installed using this method in Canada.

The Nass River Bridge is one of the largest industrial bridges in B.C., which was made affordable to the owner as a result of the innovative design concept and erection scheme prepared by Associated Engineering.




Consulting Engineers of Saskatchewan

Award of Excellence
North Battleford Comprehensive High School

In selecting Associated Engineering for the Award of Excellence in the Building Science category, the Judges commented, "In all engineering problems, there is always a question as to how far one goes - how deep do you go into the problem. We were most impressed with, as the title says, "Attention to Detail ..." This was a project in which an engineering problem was given thorough treatment - an exhaustive investigation. And it paid off. The result was a substantial savings in heating and energy costs, while maintaining a healthy comfortable working environment."

Since opening in 1969, persistent problems with occupant comfort and high utility costs have plagued the high school. Although adequately sized, the mechanical system was unable to maintain acceptable space temperatures.

Associated Engineering adopted an investigative approach, using a multi-disciplinary team. All aspects of the school that had a bearing on occupant comfort were examined. This investigation discovered many concealed deficiencies that contributed to sub-par mechanical system performance.

Associated Engineering's solution involved simultaneous repairs and upgrades to the building envelope and air handling system. Consequently, utility costs decreased and occupant comfort has improved.





Fraser River Estuary Management Program, Development Award

Marina Garden Estates, Delta, B.C.
Marina Garden Estates Ltd.

Marina GardenThe Marina Garden Estates project is a 83 hectare residential/commercial/marina complex located near Ladner, B.C. The development, which incorporates a golf course, clubhouse, hotel, commercial centre, primary school, and 1400 lot subdivision, is located adjacent to the Ladner Marsh Wildlife Management Area and along Green and Ladner Sloughs, near the Fraser River. Each of the water courses has significant fisheries, water fowl, and wildlife habitat resource values. The regulating authorities, coordinated by the Fraser River Estuary Management Program (FREMP), were concerned about any potential discharge of stormwater containing suspended solids and pollutants from urban streets, and herbicides and fertilizers from the golf course.

Marina Gardens Estates engaged Associated Engineering to review the stormwater discharge requirements, complete detailed design, prepare contract documents, and provide construction inspection and contract administration services. Associated Engineering developed a stormwater treatment pond system using a series of detention ponds planted with carefully-selected aquatic plants to provide passive treatment of the stormwater. A series of weirs and pump station control water levels by limiting the rate of water passage through the pond system, and permitting tidal water to mix with the stormwater in the pond system at high tides.

The upstream ponds above the pump station trap sediment and also reduce nutrient and solids loading. The downstream ponds form a marsh habitat with tidal mixing. The ponds are planted with native wetland plants to facilitate nutrient conversion for microbiological activity. The entire area forms part of a natural park with walkways and bridges built across the weirs.

A floodbox, 1900 m river bank protection, flood retaining walls, and precast concrete bridge were also incorporated in the design as well as all roads and utilities for the subdivision.

The Fraser River Estuary Management Program felt this project represents an exceptional example of how economic development and environmental quality can be balanced in a sustainable way.

Project sheet


Precast/Prestressed Concrete Institute Award:

King George Flyover, Surrey, B.C.
B.C. Ministry of Transportation and Highways

King George 1Because of poor ground conditions, the 115 m-long, two-lane King George Flyover was restricted to a low profile superstructure for its 43 m main span and two 36 m flanking spans. The Ministry had designed a bridge in structural steel for the crossing, but the local precast industry persuaded the Ministry to offer an alternate design prepared by Associated Engineering in precast concrete. When tendered, the concrete design proved to be 10% less costly overall as a result of a 25% saving in the cost of the girders.

Associated Engineering's design utilized twin, trapezoidal-section, precast- concrete, box girders with cast-in-place concrete deck. Intermediate piers comprised twin column bents, while all foundations were supported by driven, steel-pipe piles.

King George 2The girders comprised long precast segments, five per girder, connected by cast-in-place field splices and site post-tensioning. The hybrid-girder design greatly improved the efficiency and cost-effectiveness of the concept, and provided an elegant low-maintenance structure for this highly-visible urban flyover.





 
 

About AEWaterTransportationInfrastructureEnvironmentalNews RoomAE TodayCareersContact UsSite MapHome