|
1 B. Vallance and 2 D. Jamieson
Contact: vallanceb@ae.ca
1 Associated Engineering, Calgary, Alberta
2 City of Calgary, Engineering Services Department, Waterworks
Division
ABSTRACT
Faced with more stringent regulations and growing public expectations
regarding drinking water quality, the city of Calgary's Glenmore Water
Treatment Plant was in need of upgrading if it was to serve the City
into the next millennium. A comprehensive study and pilot programme
was undertaken to determine how best the plant could be upgraded to
meet the water quality and demands for the foreseeable future. The result
was a four phase strategic plan, the first phase of which was to upgrade
the existing facilities to meet improved particulate removal and disinfection
goals.
This paper will present the development of a clearwell design that would
meet the disinfection goals while also providing the plant with much needed
operational storage. Various site constraints and design criteria that
needed to be addressed while meeting the dual requirements for disinfection
and operational storage will be discussed. These will include:
- varying demands throughout the year
- physical site limitations
- maximizing use of existing clearwell storage
- minimizing headloss conditions to reduce excavation costs
- limiting chlorine residual levels to avoid exacerbating finished water
taste and odour
- ceasing prechlorination during periods of high source water organics
levels
- ensuring disinfection byproducts would not exceed the established
goal
- additional operational storage to provide the operator adequate time
to react to variables
The new AEP Guidelines for disinfection which now focus on removal of
protozoan cysts and viruses will be presented as they apply to the Glenmore
WTP.
On the basis of the required operational storage and disinfection CT,
the size, arrangement and T10 for the clearwell will be discussed
and how the varying demand during different seasons of the year was taken
into account in arriving at the final sizing and depth of the clearwell.
The opportunity to reduce construction costs and the analyses that lead
to the final design will also be presented.
KEYWORDS
Clearwell, Disinfection, Chlorine, Giardia, CT, Water Quality
INTRODUCTION
The Glenmore Water Treatment Plant, constructed in three phases
in 1933, 1957 and 1965, is a conventional treatment plant comprising coagulation,
hydraulic flocculation, crossflow sedimentation, filtration and disinfection.
It obtains its water from the Elbow River impounded by the Glenmore Dam.
In 1992, the City of Calgary commenced the Glenmore Water Treatment Plant
Upgrade Study based on goals identified in a scoping study completed the
previous year. The study, which included a comprehensive pilot plant evaluation
of several unit processes, chemical coagulants, disinfectants and operating
procedures, resulted in a number of recommendations contained in a four
phase upgrading plan. Phase 1 provides basic upgrading of the existing
plant to improve its reliability and to enable it to meet current and
foreseeable regulatory requirements related to water quality. Phase 2
will expand the plant's capacity by 200 ML/d, or more as deemed appropriate.
Phases 3 and 4 will address alternative disinfection and waste management
respectively when these issues arise.
Construction on Phase 1 improvements commenced in 1996 with the addition
of rapid mix facilities ahead of the flocculators, replacement of filter
media in all twenty four filters and piping additions to allow a filter-to-waste
stage in the filter backwashing procedure. All three projects are designed
to assist in meeting future water quality goals. They do not, however,
constitute a departure from previous treatment processes and would have
been required in the normal course of time without regard to changing
regulatory requirements.
A major change in regulatory requirements for disinfection of potable
water supplies is contained in the Standards and Guidelines for Municipal
Waterworks, Wastewater and Storm Drainage Systems recently introduced
by Alberta Environmental Protection (AEP). The disinfection guideline,
based on the Surface Water Treatment Rule (SWTR) and the interim Enhanced
Surface Water Treatment Rule (ESWTR), both promulgated by the United States
Environmental Protection Agency (USEPA), embodies the concept of the product
of disinfectant residual concentration and contact time, commonly termed
CT. Compliance with the new guideline will require the City to construct
a large clearwell for filtered water storage on the Glenmore Water Treatment
Plant site. The clearwell and its accompanying treated water pump station
represent a substantial capital investment and significant change to how
the plant has previously been operated.
WATER
QUALITY
General
The object of the Phase 1 improvements, of which the proposed clearwell
is an integral part, is to ensure continued high quality water production
including the removal and/or inactivation of cysts, pathogenic bacteria
and viruses and the reduction in levels of turbidity and organic matter.
These water quality parameters and regulations governing them, must be
taken into account in developing design concepts for the clearwell and
associated pump station.
Alberta Environmental Protection (AEP) Guidelines
Potable water quality has to meet the requirements of the Standards and
Guidelines for Municipal Waterworks, Wastewater and Storm Drainage Systems,
recently updated by AEP. These guidelines require, as a minimum, that
surface water be treated by chemically assisted rapid sand filtration
and disinfection. As defined by the guidelines, conventional treatment
meeting this requirement includes chemical mixing, coagulation, flocculation,
solids separation and filtration; the unit processes employed at the Glenmore
Water Treatment Plant. Disinfection may be achieved by chlorine, chlorine
dioxide, chloramines, ozone or a combination of one or more of these disinfectants.
The primary aim of such treatment is the production of water that is free
of pathogenic organisms, bacteria and viruses. Secondary aims are palatability
and aesthetic appearance.
Treatment of surface water in accordance with AEP guidelines will be
considered satisfactory based on specific levels of Giardia removal/inactivation
directly related to known concentrations of cysts in raw water. Relatively
unpolluted raw water with a cyst concentration less than 1 per 100 L will
require 3 log reduction/inactivation, while raw water with a cyst concentration
greater than 100 per 100 L will require in excess of 5 log removal. Table
1 reproduces a similar table contained in the AEP guidelines.
Table 1. Level of Giardia
Reduction
Raw Water Giardia Levels
(Geometric Mean) |
Recommended Giardia Log Reduction |
|
< 1 cyst/100 L |
3 log |
|
1 cyst/100 L - 10 cysts/100 L |
3 log - 4 log |
|
10 cysts/100 L - 100 cysts/100 L |
4 log - 5 log |
|
> 100 cysts/100 L |
> 5 log |
This level of Giardia removal/inactivation is higher than that previously
required by most regulatory agencies in North America, where 3 log removal
was normally mandated regardless of the background level of cysts in the
raw water. It reflects the growing concern over the presence of Giardia
and Cryptosporidium in raw water, particularly to which cattle and other
animals have ready access. No easy and reproducible method of detection
and enumeration presently exists for Cryptosporidium oocysts. Furthermore
they are more difficult to remove than are Giardia cysts. AEP, following
the lead set by the USEPA in its interim ESWTR, has established the higher
removal/inactivation levels for Giardia, believing they will provide greater
protection also against Cryptosporidium. There has been some discussion
about establishing specific Cryptosporidium levels in the final ESWTR,
to be promulgated in the year 2000. In view of the difficulties being
encountered in collecting relevant information on this organism, including
methods of detection and enumeration, this is not likely. AEP has stated
that Giardia removal/inactivation will remain the sole criterion for determining
satisfactory protection against cyst contamination for the foreseeable
future.
AEP recognizes that Giardia cysts are removed in a well operated conventional
water treatment plant. Accordingly, a credit for 2.5 log reduction of
Giardia will be given for such a plant, excluding disinfection, if it
meets the following turbidity reduction limits:
- When source turbidity is greater than or equal to 2.5 NTU, the filtered
water turbidity shall be less than 0.5 NTU in at least 95% of the measurements
made each calendar month.
However, the filtered water turbidity may exceed 0.5 NTU but not exceed
an upper limit of 1 NTU in more than 5% of the measurements made each
calendar month. The filtered water turbidity shall not exceed 2 NTU at
any time.
- When source turbidity is less than 2.5 NTU, the filters shall achieve
either:
- An 80% reduction in source turbidity based on an average of the
daily turbidity reductions measured in a calendar month, or
- a filtered water turbidity of less than or equal to 0.1 NTU.
Continuous monitoring of actual cyst or cyst-sized particles will not
be a prerequisite for this credit. Although the AEP guidelines do allow
for greater than 2.5 log Giardia reduction credit to be granted for a
filtration system (AEP Standards and Guidelines 2.2.4 and 4.1.5.1 (7))
this would require the use of particle counting or microscopic particulate
analysis data. The collection and use of such data would be onerous and
expensive but could be worthy of future consideration.
Protozoans
The actual Giardia log reduction/inactivation required is related to the
geometric mean of the cyst concentration in the raw water. It will be
subject to negotiation between the City and AEP when the City renews its
licence to take water from the Elbow River. Based on the City's records
of cyst concentration in the Glenmore Reservoir water, Figure 1 and on
discussions with AEP representatives, the Glenmore Water Treatment Plant
will be required to achieve in the order of 4 - 4.5 log reduction/inactivation
of Giardia. Of this amount, the plant should be granted a 2.5 log removal
credit for chemically assisted filtration, leaving 1.5 - 2 log inactivation
(4 - 4.5 log minus 2.5 log) to be achieved by disinfection.
It is worth noting that the stringent water quality requirements, particularly
the need to remove protozoans such as Giardia and Cryptosporidium, are
a direct consequence of contamination of the watershed upstream of the
Glenmore Dam. The cost of complying with these requirements, both in the
capital construction cost and in the plant operating cost, is high. This
high cost of treating water to ensure that it is safe for public use mandates
serious consideration of watershed protection measures.
Turbidity
In accordance with the AEP guidelines, credit for Giardia cyst removal
in the treatment process will be solely dependent on achieving the turbidity
reduction required by these guidelines. Experience has shown that, under
most conditions, the Glenmore plant can achieve the turbidity reduction
levels required, albeit, at times, at less than the plant's design capacity.
The plant improvements already completed under Phase 1 are expected to
allow the turbidity reduction levels to be achieved under all raw water
conditions at a production rate of 300 ML/d.
Natural Organic Matter
Natural organic matter (NOM) in the raw water as indicated by the level
of total organic carbon (TOC) varies seasonally, with a higher level in
spring and summer particularly during run-off. During these periods of
higher TOC about half is in soluble form and is relatively unaffected
by chemical coagulation, passing straight through the pretreatment and
filtration stages. The particulate fraction of the TOC is removed in the
treatment process. Because trihalomethanes (THM's), which can be carcinogenic
in prolonged dosages, are formed when organic matter is chlorinated it
is prudent to delay chlorination until after filtration, i.e. until much
of the TOC has been removed. The proposed clearwell will provide contact
time for post filtration primary disinfection. Until that time, however,
contact time provided by the sedimentation and filtration stages is essential
for effective disinfection with chlorine.
Notwithstanding prechlorination, the level of total trihalomethane (TTHM)
formed at the Glenmore plant is well below the Guidelines for Canadian
Drinking Water Quality (GCGWQ) interim maximum acceptable concentration
(IMAC) of 100 g/L. There is however, little room for complacency in this
fact for two reasons; the level of TOC is likely to continue increasing
due to agricultural and other activities in the watershed, and future
TTHM allowable limits will probably be further reduced, reflecting the
public's growing concerns about potentially harmful disinfection byproducts
in treated water. The first factor, once again points to the need for
watershed protection while the second reinforces the need for continuing
vigilance in water treatment operations and further research into alternative
methods of disinfection.
WATER
QUANTITY
Plant Capacity
The Glenmore Water Treatment Plant was designed with a maximum capacity
of 640 ML/d. It has been unable to achieve this production rate and meet
acceptable water quality standards however, for the past number of years.
This is due in part, to the increasingly stringent water quality standards
compared to those prevailing at the time the plant was built. The plant's
nominal capacity of 640 ML/d cannot be achieved even when raw water conditions
are good. Under poor raw water conditions the plant production rate must
be severely curtailed in order to comply with current water quality goals.
The Phase 1 improvements are intended to ensure that the plant will be
capable of meeting present and foreseeable future quality requirements
under all raw water conditions at a capacity of 300 ML/d. The 300 ML/d
rate appears to be the limit for particulate removal under the most difficult
to treat conditions for the existing sedimentation and filtration components.
Much higher rates of production will be possible under more favourable
raw water conditions, and for this reason, the Phase 1 plant improvements
will be hydraulically designed for 500 ML/d.
Construction Staging
Improvements to the chemical mixing and filtration components in Phase
1 have been completed. Final design of the remaining components of the
improvements, the clearwell and pump station, will be completed this year.
Construction of Phase 2 improvements, which will add a further 200-300
ML/d to the treatment capacity, will be undertaken as water demand dictates
and may be completed in two or more stages. Precisely when these improvements
will be needed is of particular importance because the timing could affect
some aspects of the clearwell and pump station design; specifically the
elevations of these two structures.
Clearwell & Pump Station Elevations
The top water level for the Phase 1 clearwell was established to allow
gravity flow into it from the future Phase 2 filters. The pump station
elevations were determined, in turn, by the clearwell elevations and other
hydraulic considerations. Provision for gravity flow from Phase 2 requires
that the clearwell floor elevation be approximately 2.0 m lower than it
would need to be if the clearwell were to be used only for Phase 1, i.e.
for the existing plant. Ozonation facilities, should they be constructed
as part of the Phase 2 improvements, would necessitate construction of
an intermediate pump station between the ozone contact chamber and the
filters.
Should the Phase 2 improvements not be required within the next 10-15
years, there would be little justification in building a clearwell at
the lower elevation needed to accommodate gravity flow from this future
expansion. The increased excavation costs are significant and, even without
a rigorous economic analysis of sunk costs versus future operating costs,
suggest that intermediate pumping, when required, would be a wiser choice.
The likelihood of ozonation in the future with its need for associated
pumping facilities supports this alternative. For these reasons, projections
of population growth and water demands were revisited during the Clearwell
and Pump Station Concept Review of January 28, 29, 1998. The purpose of
this last review was not so much to establish the size of treatment components
as to determine when they were most likely to be needed.
Water Demand Projections
Water supply projects, including intakes, pump stations and treatment
plants, have traditionally been designed to serve maximum day demands;
distribution system reservoirs being provided to accommodate hourly demand
fluctuations, fire demands and other emergency requirements. These water
demands are estimated using projected population numbers, per capita consumption
and daily and hourly peaking factors, among other things. The projected
peak day and average day water demands for 1997 - 2019, using the City's
population projections and per capita water demands are shown in Figure
1. Superimposed on the peak day water demand line is the Glenmore Water
Treatment Plant capacity, including Phases 1, 2a and 2b, and the Bearspaw
Water Treatment Plant capacity.
Figure 1. Water Demand Forecasts and Proposed
Plant Phasing
Phase 2 Implementation
Figure 1 shows, with the Glenmore plant producing a minimum of 300 ML/d
and assuming full production from the Bearspaw plant, there should be
little difficulty in meeting most peak day water demands for the next
10-12 years, perhaps longer. Moreover, peak day demands tend to occur
during prolonged dry periods when the most difficult raw water conditions
have passed. At these times production from Glenmore could be increased
above 300 ML/d. There is always the possibility however, of peak day demands
occurring earlier in the year, when such an increased production rate
might not be possible.
As stated earlier, water treatment plants have traditionally been designed
to meet peak day demands. These peaks in the case of most larger North
American communities, including Calgary, are caused mainly by lawn watering.
It is a matter for debate whether we should continue to spend large sums
on capital projects dictated by the need to provide water for unrestricted
lawn irrigation. Communities with limited water resources, such as those
relying on groundwater, often curtail lawn watering during summer months
as a matter of course. The City of Calgary has had good response in the
past when it has appealed for water use restraint during potential shortages.
Provided such appeals are not too frequently made, it is likely that any
shortfall in production during peak demand times could be offset by a
reduction in lawn watering.
It would appear that the Phase 2 expansion to the Glenmore plant is most
likely to be required after the year 2012 or thereabouts. That being the
case, the clearwell elevations should be established to enable gravity
flow from the existing plant without regard to Phase 2.
Water Demand Forecasts and Proposed Plant Phasing
DISINFECTION
Introduction
The City of Calgary employs chlorine for disinfection at both its water
treatment plants, Glenmore and Bearspaw. At Glenmore sufficient chlorine
is added to the raw water prior to coagulation to maintain a free residual
throughout the treatment process.
Additional chlorine is dosed after filtration to ensure a free residual
of 0.6-0.7 mg/L entering the distribution system. Prior to 1992, free
residual entering the distribution was maintained at a lower level, 0.2-0.3
mg/L, to avoid chlorinous taste complaints. This lower level however,
was insufficient to guarantee a free chlorine residual throughout the
system and therefore increased to its present level.
An increased number of taste and odour complaints noted in 1992 were
largely due to raising the chlorine level in the distribution system;
a common experience whenever a change of this nature is made to the disinfection
procedure. There was a noticeable decrease in taste and odour complaints
in 1993 and subsequent years, indicating widespread acceptance of the
slight increase in chlorine taste at the tap.
Disinfection Options
The more stringent Giardia removal/inactivation requirements of the new
rule will directly affect the operation of the Glenmore Water Treatment
Plant and largely determine the size of the clearwell to be provided under
the Phase 1 improvements.
Two possible technologies exist to meet disinfection goals, namely chlorination
or ozonation. Chlorination is a proven process already practised at the
plant and familiar to operators. In conjunction with the proposed, new
clearwell it can meet the disinfection goals in a cost effective manner.
Ozone is a highly effective disinfectant and requires only short contact
times, usually in the order of 10 minutes. Consequently, its use would
obviate the need for a large clearwell. However, its use presents the
following significant challenges:
Ozone should be applied prior to filtration so any ozone byproducts such
as aldehydes and Assimilable Organic Carbon (AOC) are absorbed by biological
activity within the filters. If applied upstream of clarification, the
ozone system would need to be larger, as raw water exhibits a significantly
higher ozone demand than clarified water. If applied downstream of filtration
there would be an increased potential for bacterial regrowth within the
distribution system. Chlorination would still be required for secondary
or residual disinfection, and there is unlikely to be any substantial
reduction in the annual consumption of chlorine.
There is no tolerance within the existing hydraulic grade to accommodate
ozonation unless intermediate pumping is also employed. Furthermore, as
a Cryptosporidium goal was unlikely in the foreseeable future, installing
ozone now in anticipation of this possible, future goal offers few advantages.
Lastly, net present value of capital and operating costs for intermediate
pumping and ozonation are unlikely to be lower than those of the chlorination
option. Consequently, it was concluded that the use of chlorination in
conjunction with a new clearwell is the correct approach towards meeting
current disinfection goals.
Trihalomethanes & Prechlorination
As discussed previously, any treatment strategy should ensure the removal
of as much organic matter as possible prior to the addition of chlorine,
to minimize the formation of trihalomethanes (THM's). The worst condition
for THM generation occurs in the spring when higher levels of particulate
and soluble NOM are experienced. With prechlorination, this can lead to
significantly elevated THM concentrations.
Consequently, it was decided the clearwell should be of sufficient size
to meet disinfection goals using post-filtration chlorination only during
the spring and for flows up to 300 ML/d. By contrast, during winter and
summer, NOM levels are much lower, in a more soluble form and relatively
unaffected by chemical coagulation, so prechlorination should cause only
minimal increases to THM concentrations in the treated water compared
to the use of post filtration chlorination. Prechlorination, to some extent,
was therefore acceptable during the winter when lower organic levels would
result in lower THM concentrations. Sufficient contact time would be provided
jointly within the pretreatment process and new clearwell to meet disinfection
goals for flows up to 300 ML/d.
Clearwell Size
Both 40 and 50 ML clearwell sizes have been considered. 50 ML is the maximum
practical size for the structure considering the site available, and it
makes most efficient use of the site. Tables 2 and 3 indicate the available
disinfection capacity of 40 and 50 ML contact capacity clearwells for
various seasons, based on the following:
- A 2 log Giardia inactivation goal for the disinfection system.
- Clearwell T 10 /T = 0.7.
- "C" = 0.7 mg/L of chlorine.
- A pre-chlorination T 10 /T = 0.45 within the existing cross
flow clarifiers and 0.7 in the filters.
Table 2. Disinfection Capacity for 40 ML Clearwell
|
40 ML Contact Capacity |
Winter |
Spring |
Summer |
| CT from Clearwell |
155 |
205 |
410 |
| If Clearwell T10=0.77, add |
15 |
20 |
40 |
| If prechlorination used, add |
125 |
n/a |
n/r |
| Sub-total (ML/d) |
295 |
225 |
450 |
| If "C" increased to 0.77, add |
25 |
20 |
>50 |
| Total Disinfection Capacity (ML/d) |
320 |
245 |
>500 |
n/a - not advisable n/r - not required
Table 3. Disinfection Capacity for 50 ML Clearwell
|
50 ML Contact Capacity |
Winter |
Spring |
Summer |
| CT from Clearwell |
195 |
255 |
510 |
| If Clearwell T10=0.77, add |
20 |
25 |
50 |
| If prechlorination used, add |
125 |
n/a |
n/r |
| Sub-total (ML/d) |
340 |
280 |
>600 |
| If "C" increased to 0.77 mg/L,
add |
30 |
25 |
>50 |
| Total Disinfection Capacity (ML/d) |
370 |
305 |
>650 |
n/a - not advisable n/r - not required
Table 2 indicates that for a 40 ML clearwell:
- Prechlorination must be used for all flows above 170 ML/d in the winter
and 225 ML/d in spring. To meet summer peak flows of 500 ML/d either
"C" could be increased to 0.77 mg/L or a low level of pre-chlorination
applied.
Table 3 indicates that for a 50 ML clearwell:
- Prechlorination must be used in the winter for all flows above 215
ML/d but "C" can be maintained at or below 0.7 mg/L.
- There is just sufficient capacity to meet a spring design flow of
300 ML/d without prechlorination, if "C" is raised to about
0.77 mg/L.
- There is sufficient capacity to meet summer peak flows of 500 ML/d
with "C" at or below 0.7 mg/L and without prechlorination.
From these results it is concluded that a 50 ML contact capacity clearwell
should be installed. A smaller capacity would fail to meet the disinfection
system goals, particularly during periods of elevated organics in the
spring.
OPERATIONAL
STORAGE
In addition to providing the necessary contact capacity, adequate
operational storage should also be provided in the clearwell. As the plant
is manned continuously, it was established that operational treated water
storage on site should provide a minimum of 30 minutes at the average
design flow of 300 ML/d (6.2 ML). This would afford the operator sufficient
time to react to an upset condition.
The existing clearwell located beneath the filters has a capacity of
approximately 11.4 ML. This equates to a nominal 55 minutes of storage
at 300 ML/d. The locations of the filter outlets and the difficulty of
providing acceptable baffling make it impractical to utilize the existing
clearwell for contact storage. However, it still offers valuable balancing
storage and as much use as possible should be made of this asset.
Initially, it was proposed the Phase 2 plant hydraulic grade would dictate
the minimum water level in the new clearwell. At a flow of 500 ML/d this
would be 1091.69 m, only slightly above the existing clearwell floor elevation
of 1091.20 m. The existing clearwell level would fluctuate in synchrony
with the 0.5 m balancing level variations available in the new clearwell
and so offered slightly less than 2.0 ML of additional balancing storage.
See Figure 2. Consequently, the existing clearwell would be always nearly
empty and little use would be made of the possible 11.4 ML of storage.
Consideration was given to providing a level control valve on the outlet
of the existing clearwell that would allow the existing clearwell level
to rise above the hydraulic gradient and provide approximately 9.5 ML
of additional balancing storage as shown in Figure 2. The outlet valve
would modulate based on new clearwell level. If the new clearwell level
fell, the valve would open allowing balancing volume within the existing
clearwell to be accessed.
However, there were some serious disadvantages to this. To fully utilize
the existing clearwell storage would require leaving the new clearwell
at its initial design elevation. This would be a very expensive way to
provide operational storage. Also, placing complete reliance on a control
valve on such a critical conduit was considered an unacceptable risk.
So the arrangement finally selected was to elevate the new clearwell
as high as the hydraulic profile from the existing clearwell would safely
permit. The new clearwell would have an extra 0.5 m water depth to provide
approximately 4.5 ML operational storage which together with 2.0 ML storage
for the same 0.5 m depth in the existing clearwell, would meet the required
minimum.
Figure 2. Clearwell Elevation Options
SUMMARY
The new AEP Guidelines mandate a disinfection strategy based on
the CT concept for removal/inactivation of viruses and protozoan cysts.
For the raw water cyst concentrations at the Glenmore Water Treatment
Plant, the governing goal is a 4.5 log removal/inactivation of Giardia
cysts, with a 2.5 log credit for removal through the filtration process.
Based on sound economics, the decision to continue with chlorine for
primary and secondary disinfection will require a 50 ML contact capacity
clearwell to achieve the required 2.0 log inactivation of Giardia. Although
arguments could be made for a bigger clearwell - to completely avoid prechlorination
and reduce TTHM's - site constraints present significant costs for anything
larger. Furthermore, by nature of the NOM being almost completely soluble
for most of the year, moving the primary chlorine injection point downstream
of the filters will have little impact on annual TTHM's.
The approach has therefore been to design the clearwell to meet the entire
CT requirement during spring - when NOM is high and contains significant
particulates that can be removed by filtration - with a small, 10% increase
in the chlorine dose. During summer, CT can be met with the current, 0.7
mg/L, chlorine residual. For the winter, when NOM is typically very low,
prechlorination will be used to supplement the available CT through the
clearwell to achieve the overall CT requirements.
Costs were a significant factor in selecting operational storage. To
maximize use of the existing 11.3 ML clearwell would require locating
the new clearwell CT storage below the existing, and providing flow control
between the two. This was considered too expensive - to locate the new
clearwell so deep; and too risky to place complete reliance on a control
valve for all operational storage. A total of almost 7 ML of operational
storage will be provided - 2 ML in the existing clearwell and a little
less than 5 ML in the new. This will offer over 30 minutes storage at
a design flow of 300 ML/d; sufficient for the operator to react to a plant
upset.
The strategy adopted for the design of this clearwell has been to ensure
compliance with the disinfection regulations, while minimizing current
capital expenditure. By utilizing the existing facilities, the clearwell
size has been optimized. Its construction cost has been reduced by elevating
it to the maximum hydraulic grade. It is recognized that the Phase 2 plant
will need to include intermediate pumping to achieve this hydraulic grade,
but in view of the anticipated 15 year horizon for Phase 2, capital expenditure
now could not be justified.
|