David I. Harvey, P.Eng.
Associated Engineering, Burnaby, B.C.
Contact: nharveyd@ae.ca
SUMMARY
Recent initiatives on British Columbia Ministry
of Transportation and Highways bridge projects have demonstrated
that better value can be obtained through design innovation.
As a result of the Ministry including Value Engineering
clauses into the bridge construction contracts, the contractor
was able to offer cost-saving alternative designs which
were tailored to the specific constraints and requirements
of each project. Five Value Engineered bridge designs were
offered in 1996 and 1997. These resulted in a net savings
of over $1 million. The owner obtained better value through
the integration of design with construction and the incentive
of the Value Engineering clauses. All five designs involved
the creative use of precast concrete bridge girders.
INTRODUCTION
A major component of the B.C. Ministry of Transportation
and Highways (MoTH) new construction program in recent years
has been the Vancouver Island Highway. The 300 km long $1.3
billion road has been designed to four-lane arterial and
freeway standards. Some 150 bridges were needed for grade-separation
and watercourse crossings.
In recent years, the bridge construction contracts have
included Value Engineering clauses. These clauses encourage
the contractor to propose alternative designs. Where these
offer the Ministry a cost or schedule advantage, with no
reduction in quality, they will be considered. The incentive
offered to the contractor is 50% of the net savings in addition
to any material or construction technique preference.
Experience in applying the clauses suggests that savings
can accrue through material competition, higher design efficiency,
elimination of unnecessary features, and improved constructibility.
The bridge projects described illustrate how existing structural
systems can be developed and original designs revised to
save costs. This was done without sacrificing durability,
while maintaining the quality and elegance prevalent in
successful bridges.
VALUE
ENGINEERING
Recent MoTH bridge construction contracts have included
Value Engineering clauses, along with an encouragement to
submit any number of Value Engineering Proposals (VEPs)
during the contract term. The Ministry will not accept VEPs
that could negatively impact existing approvals or bridge
aesthetics. The contractor cannot assume tender acceptance,
or prepare a claim based on a VEP.
To be considered, a VEP must offer a tangible benefit to
the owner. The substitution must be functionally equal or
superior, while reducing risk, initial or life-cycle costs,
or a schedule advantage. In preparing VEPs, the original
design criteria must be used. A change in contract conditions
does not qualify as a VEP.
VEPs may involve changes in materials, products work method,
construction sequence and especially design. They are evaluated
usually on the basis of net cost saving. This is calculated
by adding to the negotiated cost of the VEP:
- The contractors cost of developing the VEP.
- The owners cost of evaluating the VEP.
- Any resulting administrative or management costs to
the owner.
The driving force for submissions is the Value Engineering
Incentive. Generally, this results in 50% of the net saving
being earned by the contractor. There are, however, disincentives,
which can be summarized as follows:
- The contractors cost in developing a VEP for which
he has no certainty of recovery.
- The time taken to prepare a complete design for a VEP
submission by the contractor, his suppliers and his consultant.
- The time taken by the owner to evaluate, comment on,
and negotiate a VEP, over which the contractor has no
control.
- The period of delay during which the contractor can
only execute work unaffected by the VEP, and cannot procure
materials for either the original or alternative designs.
- The uncertainty of obtaining acceptance of work carried
out on the VEP prior to the supplemental contract agreement
being implemented.
The following bridges involved either partial or complete
redesigns. All resulted from VEPs, which were accepted following
minor adjustments requested by the Ministry. All involved
the substitution of superstructure systems along with either
adjustments to the original substructure or a new design.
BLOEDEL
CREEK BRIDGE
This
bridge is a single 45.1 m span, south of Courtenay, B.C.
Twin 11.4 m wide roadways on separate superstructures cross
12 m above the creek at 15 degrees of skew. The control
line curvature is on 1800 m radius, which results in a deck
superelevation of 3.4% (Figure 1).
The Bloedel Creek bridge was originally designed using
three steel plate girders per superstructure, 1.9 m deep,
at 4.2 m centres. The deck was a minimum of 275 mm thick.
Most of the zone between abutments was not accessible for
construction purposes because of environmental restrictions.
The contractor wanted to reduce costs by using precast
concrete girders. This could only be economical if the original
three-girder superstructure system was used. This would,
however, result in higher loads than concrete girders typically
support over this span, and would stretch the limits of
precast girder design.
The selected girder is a standard 2.3 m deep I-section.
At 46 m long, the precast girders weigh about 76,000 kg,
well above road transportation limits. The precast concrete
manufacturers plan was to transport the girders in
one piece by barge from their plant to a loading dock near
the site, and then by off-highway forestry road to the site.
Erection would be carried out using two 40 m long launching
trusses side by side, supported by falsework in front of
the abutments.
In order to use the concrete three-girder system effectively,
the superstructure needed reconfiguring. The 1 m wide girder
top flanges permitted a 250 m constant thickness concrete
deck to be used, in conjunction with a girder spacing of
4.5 m. To provide sufficient flexural capacity, a hybrid
prestressing system is used. Each girder incorporates the
following:
- 44 straight 13 mm diameter pretensioned strands.
- 12 deflected 13 mm diameter pretensioned strands.
- 36 - 15 mm diameter post-tensioned strands.
The post-tensioning consists of three draped tendons, each
with twelve strands. In order to maintain adequate cover
in the 150 mm thick girder web, oval-section ducts are used.
The post-tensioning is applied in the field in two stages.
Two tendons are tensioned prior to construction of the concrete
deck, and one after the deck concrete had attained at least
20 MPa compressive strength. All tendon anchorages are located
in the deck end-diaphragms which are widened for this purpose.
The cast-in-place diaphragms also serve as integral ballast
walls. This avoids the need for precast girder end-blocks,
which simplifies fabrication and, more importantly, reduces
the weight of the already very heavy girders. This is important
in order to maximize the span potential of the launch trusses.
Having the end-diaphragms structurally effective prior to
deck construction helps to stabilize the girders. Two intermediate
diaphragms are provided. To speed construction and save
weight, structural steel sections are used, bolted to the
concrete girders.
The multi-stage prestressing system provides sufficient
girder capacity for transportation and handling. The strength
is supplemented by the first stage of field post-tensioning
in order to provide sufficient resistance for deck concrete
placement, the largest load component. Additional post-tensioning
is then added to provide sufficient capacity to resist imposed
loading.
By using the hybrid prestressing system, the following
is achieved which would not be possible using a conventional
pretensioned girder:
- More total prestressing applied to each girder.
- Greater strand eccentricity near mid-span.
- Greater strand deflection, vertical prestress component,
and shear capacity near the girder ends.
- Better control of stresses throughout the loading stages.
This approach, coupled with a high specified strength of
70 MPa at 56 days, permitted the three precast concrete
girder concept to be used.
The additional 400 mm of structural depth was not an issue
as the bridge opening is controlled by the highway profile.
The abutments were adjusted to accommodate the revised superstructure
details. The original footings were located on bridge end
fill or bedrock and were adequate to support the additional
superstructure weight.
The Bloedel Creek Bridge is scheduled for completion in
May 1998.
WILFRED
CREEK BRIDGE
The
Wilfred Creek Bridge is one of the few multi-span, fully
integral abutment bridges in B.C. The twin 65 m long superstructures
are continuous over spans of 17 m, 29 m, and 19 m, and cross
15 m above the creek at a skew of 15 degrees. The deck widths
are 11.9 m northbound and 12.9 m southbound. The control
line is on a 1000 m radius which results in a 4.8% deck
superelevation (Figure 2, Figure 6). The bridge is supported
on driven steel pipe piles and concrete piers. The site
is immediately south of Courtenay, B.C.
Originally designed with four 1.2 m deep continuous steel
plate girders per superstructure and a 225 mm thick deck,
the bridge was redesigned using pretensioned concrete I-girders.
These are 1.7 m deep and are spaced at 3.5 m or 3.8 m centres,
similar to the steel girders. To reduce the quantity of
deck reinforcement, the selected deck thickness is 250 mm.
As the bridge opening is governed by the highway profile,
the additional superstructure depth was acceptable.
The contractor was installing the piles while investigating
the Value Engineering Proposal. As a result, only superstructure
changes could be contemplated, and no opportunity was available
to investigate a different number of girders. With a maximum
weight of 32,000 kg, the girders are readily transportable.
As the girders are inherently stiff and only lightly stressed,
no intermediate diaphragms are necessary. The centre span
units were positioned using a steel launching truss resting
on the intermediate support bents.
 In
order to provide the maximum structural efficiency and constructibility,
the simply-supported girders were placed on the abutments
and piers, while projecting reinforcement was embedded into
the concrete support-diaphragms. No bearings or joints are
used. After placing the support-diaphragm concrete, the
girders are effectively made continuous for subsequent imposed
loads. This novel approach provides a more efficient structure
to resist the deck self-weight, while also stabilizing the
girders. The tensile stresses near the girder ends are controlled
by deflecting a high proportion of the pretensioning. Twelve
of the twenty eight, 13 mm diameter strands in the centre
spans are deflected. Projecting overlapping rebars resist
the support moments. The concept of stiff built-in concrete
girders allows the deck concrete to be placed in one continuous
operation.
The girders are shorter versions of the Cowie Creek girders,
and therefore, experience comparatively low stresses. A
28 day concrete strength of 40 MPa was specified. To accommodate
the deeper superstructure, the abutment wall depth was increased
and the intermediate pier columns were shortened. In supporting
the heavier superstructure, the pile loads increased only
slightly, and the pier columns were found to have adequate
seismic load resistance without modification. The bridge
is scheduled for completion in June 1998.
COWIE
CREEK BRIDGE
This
bridge is a three-span 92 m long bridge south of Courtenay,
B.C. (Figure 3). Twin 11.4 m wide roadways on separate superstructures
cross 20 m above the creek at a skew of 6 degrees. The main
span is 37.5 m, with 27.5 m end spans. The control line
is on tangent. The deck crossfall varies, however, as superelevation
run-offs encroach onto both ends of the deck.
The Cowie Creek Bridge was originally designed using four
1.2 m deep continuous steel plate girders per superstructure,
at 3.25 m centres. A 225 mm thick cast-in-place concrete
deck is used. The zone beneath the main span is not accessible
for construction purposes.
The contractor wished to replace the steel girders with
prestressed concrete girders, by adapting the system used
for Wilfred Creek Bridge. It was determined that a similar
system could be employed for the two bridges. The 1.7 m
deep prestressed girders, weighing up to 42,000 kg, are
just within transportation weight and length restrictions.
The centre span units could be positioned using a launching
truss resting on the pier caps.
It proved to be just possible to design the precast girders
for the end-moments generated by the weight of the concrete
deck. Ten overlapping 30M hooked bars project from the top
flanges into the concrete pier diaphragms. The precast concrete
girders experience significantly higher stresses than at
Wilfred Creek. Twenty six straight strands and twenty deflected
strands of 13 mm diameter are used in the centre span girders,
which require a 28 day strength of 56 MPa.
A single intermediate diaphragm of steel angle bracing
is used at the midpoint of the centre span to assist in
stabilizing the girders during construction. As the bridge
opening is controlled by the highway profile, the 0.5 m
additional depth of the concrete superstructure was readily
accommodated by lowering the pier caps and abutment seats.
The inherent stiffness of the precast girders permitted
the deck concrete to be placed in one continuous operation.
Integral ballast-retaining walls are at each end of the
92 m long superstructure. No bearings are used at the monolithic
pier connections, but laminated rubber bearings support
the girders at the abutments.
Reanalysis of the substructure was carried out for seismic
loading with the heavier concrete superstructure. No modification
of the intermediate-support columns or footings was required.
An increase in lateral sliding resistance of the bank-seat
abutments is achieved by placing two 0.9 m deep shear keys
beneath the footings. The bridge construction is scheduled
for completion in June 1998.
TRENT
RIVER BRIDGE
The
three-span, 106 m long Trent River Bridge is located 750
m north of the Bloedel Creek Bridge (Figure 4). Twin 11.4
m wide roadways on separate superstructures cross 24 m above
the creek at a skew of about 22 degrees. The 1800 m radius
in plan requires a deck superelevation of 3.4%.
This bridge was originally designed using three 1.6 m deep
continuous, steel-plate girders per superstructure, at varying
centres of approximately 4.2 m. The deck had a minimum thickness
of 275 mm. No construction access was available in the area
beneath the main spans.
The contractor wished to replace the steel girders with
precast concrete. A rapid assessment indicated that to achieve
the maximum cost saving, the original three-girder system
would have to be retained. Additionally, by increasing the
girder spacing to a constant 4.4 m, a deck thickness of
250 mm could be used, reducing the superstructure weight.
The 40 m main span girders could be placed by using two
launching trusses supported on the pier caps. Standard 2
m deep precast I-girders could be employed, but would need
to be adapted to the high levels of loading that they would
experience. Their maximum length of 39 m and weight of 53,500
kg precluded highway transportation. However, by using barges
and industrial roads, the girders could be routed to site.
The challenge was to design the girders. The system used
for Cowie Creek Bridge was investigated. Unfortunately,
insufficient flexural capacity was available both at mid-span
and at the intermediate supports. The solution was to supplement
the pretensioned segments by applying field post-tensioning
from end to end. In this fashion, a higher total level of
prestressing could be applied, thereby increasing girder
load capacity without increasing the number of girders.
Each girder has sixteen straight and twelve deflected 13
mm diameter pretensioning strands. These strands provide
strength for transportation and handling while reducing
the required quantity of post-tensioning. Four ducts per
girders are provided, each containing seven 15 mm diameter
strands. The ducts are oval-section, 55 mm by 75 mm, in
order to maintain adequate cover in the 140 mm thick girder
web. The ducts are field-spliced prior to casting the concrete
diaphragms and subsequently post-tensioned. The tendon anchorages
are located in the cast-in-place ballast retaining walls.
All tendons are tensioned prior to deck construction, which
is carried out in one continuous concreting operation.
The specified girder concrete strength is 70 MPa at 56
days. As well as using the maximum flexural capacity of
the girders at mid-span, near the intermediate supports
maximum available shear resistance is used. This is a good
indication that the design has achieved maximum efficiency
and effectively stretched the limits of precast concrete
bridge girder technology.
To enhance stability during construction a single intermediate
diaphragm of galvanized steel WT bracing is provided at
the centre of the main span. The additional depth of the
concrete girders was acceptable and did not require any
revision to the highway profile. No bearings are used at
the monolithic pier connections but laminated rubber bearings
support the girders at the bank-seat abutments. Although
the intermediate piers did not require strengthening to
resist seismic loads from the heavier superstructure, shear
keys were added beneath the footings of the bank-seat abutments.
The substructure of the Trent River Bridge was also included
in the Value Engineering Proposal. An evaluation demonstrated
that the spacing of the pier columns could be reduced to
better balance the loading on the caps and footings. More
savings were realized by reducing the size of the pier footings.
The largest cost saving, however, was achieved by eliminating
the forty eight, vertical 32 mm diameter threadbar ground
anchors originally detailed. This was done by lowering the
footings by up to 1 m, and keying them into the site bedrock.
The Trent River Bridge is scheduled for completion in July
1998.
THE
DUKE POINT UNDERPASS
This
bridge is part of the grade-separated interchange between
the Trans-Canada Highway and the spur road to the Duke Point
Ferry Terminal near Nanaimo, B.C. The bridge carries three
traffic lanes on a 16.7 m wide deck over the four-lane divided
highway. The bridge is continuous over its 21 m, 38 m and
21 m spans. The plan alignment is part radius, part spiral,
which results in a minimum of 5.6% deck superelevation.
The bridge was originally designed as two 1.5 m deep, twin-cell,
cast-in-place, post-tensioned, concrete, trapezoidal-box
girders supported by flared concrete piers. The contractor
wanted to build a precast concrete girder bridge. Because
of aesthetic considerations and depth restriction, I-section
girders were not acceptable. As a result, a 1.4 m deep precast
concrete trapezoidal open-top box girder was used for the
Value Engineering Proposal.
 By
using three of the box girders at 6 m centres, a useful
cost saving could be achieved. Additional costs could be
saved by supporting the girders on circular discrete-column
piers, while eliminating the steel pipe piles originally
used to support the east pier and abutment. Instead, footing
subexcavation and structural fill replacement was employed.
The superstructure design uses five segments per girder
connected by cast-in-place concrete splices and field post-tensioning.
The 21 m long centre span segments are lightly pretensioned,
while the remainder are provided with reinforcement to control
handling stresses. The16 m long pier segments include local
bottom flange thickening near the piers and an integral
internal diaphragm. The girders are supported by pot bearings
on top of the columns and laminated rubber bearing at the
abutments. No intermediate or pier diaphragms are used.
The end-diaphragms retain the approach fills and accommodate
the post-tensioning anchorages.
Each girder is provided with six tendons of eleven 15 mm
diameter strands. One additional strand per tendon could
have been added if needed in the field, although this proved
to be unnecessary. Only ten strands per tendon were used
in the design. The eleventh strand is included to avoid
the provision for future post-tensioning specified by the
Ministry. Inside the box girders, 50 mm thick precast stay-in-place
forms were used. The deck was cast in one operation and
then post-tensioned longitudinally.
The bridge was completed in January 1997 and opened to
traffic a few months later. Despite the time taken to redesign
the bridge and obtain approval for the VEP, no delay in
the construction schedule occurred.
COST
SAVINGS
The following are net Value Engineering savings. Under the
contract Value Engineering clauses, the VEP savings are
shared equally between the Ministry and the contractor.
The gross design savings, i.e., prior to deduction of the
cost of assessment, cost of VEP preparation, and engineering
redesign, is about 30% higher.
DISCUSSION
The VEP savings on these bridges range from 6% to 20% of
the tender prices. In all cases, precast concrete girders
were used to replace steel girders, except for the Duke
Point Underpass where cast-in-place concrete was originally
used. It should be recalled, however, that for the three
bridges with the lowest cost savings, only the girders changed.
When this happens, an engineering evaluation of the complete
structure and some re-detailing is necessary as the superstructure
depth and weight is frequently different.
The largest savings occurred with the redesigns for the
Duke Point Underpass and the Trent River Bridge. For these
structures, the complete bridge was reengineered. Savings
in the substructure were significant and were similar to
superstructure savings.
Table 1 - VEP Cost Savings
| Bridge |
Tender Cost ($) |
VEP Savings ($) |
| Bloedel Creek |
1,400,000 |
97,000 |
| Wilfred Creek |
2,000,000 |
100,000 |
| Cowie Creek |
2,300,000 |
230,000 |
| Trent River |
2,800,000 |
400,000 |
| Duke Point |
1,500,000 |
300,000 |
| Total |
10,000,000 |
1,127,000 |
If the VEP savings are viewed as the gross difference in
cost of the materials changed, the savings are highly significant.
That this can be achieved is perhaps surprising. The bridges,
it should be realized, have already been subject to careful
evaluation and design optimization by the original designer.
On top of this, the Ministry subjects all consultant designs
to rigorous cost-control scrutiny. Savings of over 10%,
however, are appreciated as this enables more bridges to
be built for a given budget.
Why, therefore, are any savings possible? The answer, we
believe, is because there is no infallible universal system
for designing the most cost-effective bridge. The incentive
of 50% of the VEP savings will drive an aggressive contractor
to find a better way. In this case, it involved stretching
the recognized limits of precast concrete girder technology.
The contractor, however, takes a significant risk in deferring
construction while he prepares a VEP, during which time
affected work is either delayed or performed speculatively.
By allowing the contractor to take ownership of the design
via Value Engineering, the cost and schedule advantages
of design/build are available. The resulting stimulus to
be creative and develop a solution geared to the contractors
available resources often permits significant savings to
be found. By opening up the bridge design as well as construction
to competition, better value can be delivered by industry
to the owner. Always desirable, it is especially important
for publicly-funded projects.
ACKNOWLEDGMENTS
The author wishes to thank the B.C. Ministry of Transportation
ad Highways, Bridge Branch, Director Peter Brett, P.Eng.,
for permission to publish this paper. The following are
gratefully acknowledged for their contributions to the project:
Owners Representative: Vancouver Island Highway
Project Management Team.
Contractor: Wilfred Creek Bridge, Cowie Creek Bridge:
Carlson Construction Ltd.
Bloedel Creek Bridge, Trent River Bridge, Duke Point
Underpass: Emil Anderson Construction Ltd.
Precast Concrete Manufacturer and Erection: Con-Force
Structures Ltd.
|