|
S. Balkrishnan, P.Eng.
Associated Engineering, Edmonton Alberta
Contact: balakrishnanb@ae.ca
SUMMARY
Three examples incorporating some innovative
approaches used to solve bridge design and rehabilitation
problems are described. The first example deals with the
rehabilitation of a 168 m steel girder bridge damaged due
to undermining of a pier by scour. The stresses were relieved
from the superstructure, which was then used to support
pile driving equipment. Pile bents were installed immediately
upstream and the superstructure was transferred over onto
new pile bents. The second example involves modification
of a bridge to act as a water retaining structure under
flood conditions. The third example involves an interchange
with 65 skew. The economical solution was to provide a
bridge with square ends and longer spans. Post-tensioned
concrete diaphragms were cantilevered at piers to support
the exterior steel plate girders.
INTRODUCTION
Consulting bridge engineers in North America, and perhaps
worldwide, are usually working under budget and time constraints.
They are usually competing with each other to secure new
design and construction assignments. The clients, usually
public agencies or large corporations, are looking for added
value such as decreased initial and life-cycle costs, shorter
construction schedule, less adverse effect on the environment
and aesthetics. In order to meet or exceed the expectations
of the clients, given the time and budget constraints, innovative
solutions are called for. The survival and growth of a consulting
engineering business depends on the ability of the engineers
to provide creative solutions.
This paper presents three examples where innovation has
been used to meet the clients needs within the given
constraints.
1.
SMOKY RIVER BRIDGE
1.1 Background
Located 40 km south of Grande Prairie, the Smoky River Bridge
handles up to 10,000 log-haul vehicles during the harvesting
season. In July 1997, a flood rendered the 168 m long bridge
unsafe for vehicles. Without the bridge, log-haul traffic
would have to make a 130 km detour. The client required
restoration of the bridge before harvesting operations started
in the fall.

The bridge crossing over the Smoky River has been damaged
by river flood events on three separate occasions. An estimated
5000 m3 /s flood in 1972 destroyed the original
bridge and this bridge was subsequently constructed the
same year, at a more favourable location 2 km downstream.
The bridge piers are founded on spread footings on gravel.
(Figure 1). This bridge was designed to allow for higher
flood flows by providing a "fusible link" in the
east abutment approach fill. However, the course of the
river changed considerably towards the west and an estimated
4300 m3 /s river flow in 1982 washed away the
west approach of the new bridge. The bridge was able to
be re-instated and the west side was subsequently provided
with additional embankment protection.
In July 1997, subsequent to a flood estimated at 2300 m3
/s, a deep scour hole was created in the river bed immediately
upstream of the west pier. The pier was undermined, became
unstable and subsequently tilted and subsided into the scour
hole, dragging the superstructure with it. The bearings
withstood the force of resistance offered by the superstructure,
but in doing so, considerably distorted the deck and severely
damaged the plan cross bracing. The pier was still attached
and the scour hole has been subsequently infilled. The pier
still offered support to the downstream girder but pulled
down the upstream girder which now spans from the East pier
to the West abutment. The damaged bracing, settlement and
induced plan curvature made the bridge unsafe and unusable
for use by the design vehicle.
Neither the pier nor bridge superstructure were irrevocably
damaged by the movement and it was considered plausible
to reinstate the bridge by forcing the deck back to its
original level and alignment and replacing the damaged bracing
elements.
The pier could be re-used but would be required to be stabilized,
or alternatively replaced.
The bridge restoration solution involved using the existing
bridge as a work platform to construct new piled foundations,
and to raise and move the superstructure onto the new piled
piers and abutments. This type of construction had not been
previously executed on such a large bridge structure, which
challenged the project team to devise an innovative construction
plan and solution for temporary works. Adopting a fast-track
approach, detailed design was completed concurrently with
construction, saving approximately six weeks compared with
the traditional design, bid, construction approach.
1.2 Design and Construction
Before starting any construction from the bridge deck, the
superstructure was leveled and straightened. Damaged plan
bracing was removed, and the girders were leveled above
the west pier by jacking the girders off the bearings. To
act as a temporary support and sliding surface, a skid-beam
was fixed to the west pier. A Teflon sheet was placed on
the skid-beam, and the girders were jacked onto new temporary
sliding supports. Once this was complete, the girders were
jacked laterally to straighten the bridge. The buckled and
torn bracing elements were then replaced.
Once
the girders were realigned, the bridge was used as a work
platform for a crane to install piles for new piers (Figure
2). Piles were driven from the bridge deck, reducing instream
work. A steel diaphragm was designed which also acted as
a driving template to ensure that the piles were accurately
positioned. The first pile driven beside each existing pier
acted as the guide-pin for the installation of the steel
diaphragm that encased the piles and formed the new pier.
Diaphragms were fabricated in sections, transported to site,
then bolted together. The modular nature of the templates
allowed them to be quickly assembled on site while the piles
were being driven. Each pier diaphragm was then lowered
over its guide-pile and used as a template for driving other
piles. Finally, the steel diaphragms were filled with concrete,
eliminating the need to build expensive formwork and cofferdams,
and reducing the risk of spilling concrete in the river.
(Figure 3).
The use of a precast concrete pile cap allowed the work
to proceed at a faster pace than casting an integral cap.
The contractor easily positioned the cap from the bridge
deck using an 80 ton crane. Holes were left in the pile
cap above the piles to allow them to be cleaned and socketted.
Lifting frames were constructed at the piers
and abutments. (Figure 4). The frames consisted of header
beams supported by steel-pipe columns, bolted to the existing
piers and the new pile caps. At the abutments, an additional
pile was driven alongside the new pile cap to support the
header beam, as the pile cap was too small to accommodate
the pipe column. A simple sandwich bearing connected header
beams to the columns. Because the west pier had rotated
out of position, it was not attached to the column until
the bridge had been moved a few metres. To accommodate this,
a temporary support was attached to the bridge deck, on
which the header beam rested. A sheet of Teflon placed between
this column and the header beam allowed the bridge to slide
sideways. A support bracket for the column was welded and
bolted to the west pier, and the frame column was tied to
the side of the bridge.

The bridge was then raised 25 mm at all locations but the
west pier, so that the bearing could be removed, and jacked
sideways until the frame column was in position. The connection
at the west pier was then completed. The temporary column
on the bridge deck was removed, and the bridge was jacked
sideways until it reached the new substructure, 10 m upstream.
At this stage, the bridge was raised so that it could be
moved onto the new foundations. The bridge was adjusted
to its final alignment, and lowered onto the new bearings.
1.3 Environmental Impact
To restore the Smoky River Bridge, Canfor elected to construct
a new substructure for the bridge. Although not the lowest
cost, this alternative provided the best protection against
future damage by scour and floods, and had minimized environmental
impact. By using the existing bridge as a work platform,
no construction other than pile driving was required in
the river. In addition, this design increased the waterway
opening so that the 100-year return flow will pass through
the bridge with sufficient freeboard. Demolition of existing
piers has been delayed until a suitable construction window
is available, also to minimize the impact on the Smoky River.
2.
HEART RIVER BRIDGE AT PEACE RIVER
The Town of Peace River downtown area flooded during
April, 1997 during an ice jam in the Peace River. (Figure
5). The Peace River flood backed up the Heart River and
caused the high water to spill through an opening in the
Town dike at the Heart River bridge. The Town dikes have
been raised several times, most recently in 1996. However,
the deck elevation of bridge over the Heart River, which
was constructed in 1956, is lower than the top of the dike
elevation. As an interim measure the Town used to temporarily
close the breech whenever a flood is imminent. Closure was
not possible during the 1997 flood. As a result, the river
spilled out through the opening in the dike left by the
bridge.

A more suitable permanent solution was desired.
The Town of Peace River invited proposals to raise the
bridge deck elevation to be at the top of the dike. This
involves raising the bridge by 1.28 m on the south side
and 2.0 m on the north side and construction of a ramp on
the north side to accommodate two lanes of traffic. Location
and elevation of approaches presented special challenges
since the bridge is located in a heavily developed area.
The western portion of the approach road at the north side
had to remain at the existing elevation. Therefore, retaining
walls were required at each side of the ramp. Access from
the adjacent east-west road had to be closed.
An alternative to raising the bridge is to provide a "gate"
at approach to the bridge on the north and south sides,
which will be closed (manually or automatically) when water
level exceeds the bride deck elevation. Alternatives for
pedestrian and emergency vehicle access are required in
case the "gating" option is used. Some of the
disadvantages associated with the gating option are:
- It is not a permanent solution.
- Needs manual intervention if it is not automatic.
- Needs regular maintenance and testing.
- Emergency access measures are expensive.
The author presented an alternative solution to maintain
the existing level of the bridge deck. This involved modifying
the bridge structure to retain water using barrier walls
thus closing the breech in the dike. The details are shown
in Figures 6. This alternative involves placing a cast-in-place
concrete slab varying in thickness from 500 mm at the north
end to 300 mm on the south end, on top of the existing bridge
deck. The existing bridge rails will be removed and a barrier
wall will be built monolithic with the new deck slab. The
barrier walls extend into the dike to close the breech.
The new deck slab will be connected to steel girders using
shear connectors so that the structure acts compositely.
The superstructure thus modified will be able to withstand
the uplift during ice jam flood conditions assuming a design
high water level at the existing top-of-dike. Uplift restraints
should be provided at piers and abutments. The expansion
joints at each abutment will be augmented by water retaining
seals. Depending on the soil conditions, this alternative
may necessitate some additional piles at the piers in order
to carry the increased load from the structure. If the dikes
are raised in the future, the barrier walls could be raised
and the deck could be further thickened to resist the increased
uplift forces.
The effect of this alternative on the adjacent properties
and roads is small. Local regrading is required at the north
and south approach road intersections. The traffic pattern
remains the same as existing.
The Town council voted to adopt alternative 2. The bridge
modifications were completed in February 1998.
3.
A CONTINUOUS STEEL GIRDER BRIDGE WITH INTEGRAL POST TENSIONED
CONCRETE DIAPHRAGMS
This grade separation at Highway 3 East Bound Lanes and
Highway 23 South Bound lanes is at a 65° skew. (Figure
7).

A number of alternatives were studied for this flyover:
- A single span bridge with Mechanically Stabilized Earth
Walls.
- A three span bridge with skew ends.
- A three span bridge with two box girders.
Each of these alternatives presented different problems.
The soil conditions at the site were such that MSE walls
would induce high settlements and also difficult to construct
in winter. The three span bridge with skew ends would require
long expansion joints and other maintenance problems. The
three span box girder bridge would be an elegant solution
but was not amenable for future widening.
After some iterations, an innovative solution was arrived
at. This involves constructing a three span bridge with
square ends. The dimensions of the pier column had to be
restricted so that they do not encroach the required horizontal
and vertical clearances. This meant that the exterior steel
girders had to be cantilevered off an integral pier diaphragm.
(A pier cap beam below the girders would have infringed
on the clearance requirement).
An integral steel diaphragm was considered. This would
involve complete moment connection details at the site and
future widening would be more difficult. A post-tensioned
concrete diaphragm offered advantages such as ease of construction
and future extension. (Figure 8). Ducts for future post
tensioning rods were incorporated in the diaphragm.
This bridge was completed in September 1997 and is functioning
well.

4.
ACKNOWLEDGMENTS
A team approach was used in arriving at and executing these
projects. For the Smoky River Bridge, Martin Jobke, Steve
Croxford, Tamer Akkurt and Julien Henley were involved in
developing solutions along with the contractor, Surespan
Construction Ltd. Lianna Mah contributed to the write up
of sections dealing with this bridge. For the Heart River
Bridge, Steve Croxford, Helder Afonso, Michel El-Khoury
and Dusanka Stevanovic were involved in the detailed design
and construction. Larry Bodnaruk performed the hydraulic
calculations for both bridges. For the flyover, Bob Ramsey
was involved in the original review and concept development.
|