| |
Dieter G. Foessel, M.Sc., R.E.T.
Contact: foesseld@ae.ca
- Introductions: D. Foessel – Project Manager,
Infrastructure Group (Calgary)
- Thank the LGAA and Norm McInnis for inviting us to
speak to the LGAA delegates.
- The presentation will focus on why a municipality
should (and needs to) commission an Infrastructure Master
Plan (IMP)
- The benefits and uses of an IMP as a long-term planning
tool
- IMP preparation costs
- Consultant selection for IMPs.
An IMP is an investigation and analysis of a municipality’s
infrastructure systems over a 20 to 25 year design horizon
and may consist of:
- A global investigation of all of the municipality’s
infrastructure systems (i.e. water system, wastewater
system, stormwater system, transportation infrastructure,
and capital assets such as buildings)
- An investigation of an individual infrastructure system
(i.e. only the wastewater system)
- An investigation of a component of an individual
infrastructure system (water or wastewater treatment
plant, storm water retention pond, or a collector road).
- What an IMP provides:
- An assessment of the current physical condition of
a system and its ability to provide the intended service
and level of performance over the next 20 to 25 years
- An analysis of the system’s ability to met current
and long-term performance requirements in response to
anticipated development(s)
- An analysis of the system’s ability to meet
current regulatory requirements
- Determines when systems upgrades are required and
the magnitude of the upgrades
- Identifies and prioritizes the capital works upgrading
projects into short term (0 – 2 years), medium
term (2 to 4/5 years) and long-term (5+ years) based
on a risk analysis for each upgrade project identified
(Tables 6, 7 & 8)
- Provides a capital works cost estimate for each project
(Tables 6, 7 & 8)
- Provides the base information necessary for the preparation
of a long term planning document and capital works plan(s).
You can view all table/chart images in full size, they have
been shrunk down to fit this page. Righ click and View Image.
In brief, the IMP provides answers to five (5) basic questions
from an Administrator’s perspective:
- What’s my problem?
- How do I fix it?
- What do I need to do to fix it?
- When do I need to do it?
- What’s it going to cost?
Once the Administrator has the answers to these questions,
the planning component can be added and the sixth question
may be added:
6. How do I finance it?
The following tables and figures are a graphic example
of how the IMP information may be used to create a basic
planning document and to develop capital plans for infrastructure
upgrading projects.
Infrastructure systems are major capital assets that
need to be managed, maintained and periodically upgraded
if they are to provide the level of service and performance
for which they are intended. In order to do that, an Administrator
needs the information that an IMP provides so that he can
plan and manage the infrastructure system(s) in an orderly,
phased manner. Once an Administrator has the IMP information,
he/she has the necessary information for a planning document
from which short and long-term capital plans may be developed.
There a primarily three (3) reasons to commission an
IMP:
.1 To provide the Administrator with a planning document
from which short and long term capital plans may be developed.
.2 To qualify for grant funding for capital projects
under available financial assistance programs such as the
Alberta Municipal Infrastructure Program (AMIP):
- Under Section 5 of the AMIP program, “The Municipality
will need to substantiate through a Multi-Year Capital
Infrastructure Plan that it can utilize the funds within
the program time period. This plan will facilitate the
accumulation of grant funds by the municipality in order
to accommodate larger projects requiring more than one
year’s grant allocation.”
- Infromation regarding financial assistance programs
may be found on the following websites:

To comply with current AENV regulatory requirements for
municipal water systems.
- The new AENV “Standards and Guidelines for Municipal
Waterworks, Wastewater and Storm Drainage Systems”,
January 2006, contain significant changes to the Waterworks
standards and guidelines. Section 1- Waterworks System
Standards outlines the critical design and/or performance
standards of a municipal potable water system. “These
are mandatory requirements with which owners are required
to comply.”
- There are no grandfathering provisions for recently-upgraded
water systems. (The wastewater and storm drainage standards
and guidelines are unchanged from the 1997 edition).
- The Foreword section of the AENV standards and guidelines
states that, “It is recognized that not all existing
waterworks will meet the standards published in this
document. As the new standards will have a direct impact
on the safety of drinking water, Alberta Environment
expects the upgrading to be done in a reasonable period.
It is proposed that all waterworks systems that hold
an approval or registration be upgraded to meet these
new standards before 1 April, 2012. The system owners/utilities
are also expected to develop and submit to the Regional
Director a five-year capital plan before April 1, 2007
to upgrade the system. The capital plan may be developed
with Alberta Infrastructure and Transportation if eligible
for funding under the Municipal Water/Wastewater Partnership
program.”
- The preparation cost for a complete IMP (a global
IMP/or all infrastructure systems) for a town of 2,000
to 3,000 people is estimated to be approximately $110,000
to $115,000. The cost is reduced if only individual infrastructure
systems or components of systems are investigated.
- This amount appears to be a considerable amount of
money until the cost is put into perspective with respect
to the value of the capital cost of the upgrading projects
identified, and the grant funding available through existing
financial assistance programs.
- In 2004, AE prepared a global IMP for a town of 1,700
for a total cost of $95,000. 44 capital works projects
were identified estimated at a cost of $8.4M. As a percentage
of the total estimated capital project cost, the cost
of the IMP was only about 1.1%. With available grant
funding applied (say 50%), the expected cost of the preparation
of a global IMP may be less than 0.5% of the total estimated
capital works costs. $50,000 is a reasonable cost for
a document that provides a municipality with all the
information required to plan and manage the municipality’s
infrastructure systems over the next 20 to 25 years.
- IMPs are ‘living documents’. As such, they
need to be updated at least every 5 years in a stable
economy or situation. As economic conditions and regulatory
requirements change or unforeseen events occur, the IMP
or portions thereof may need to be reviewed and revised
accordingly. The revision may be easily and quickly made
at a reasonable cost since all the bulk groundwork has
already been done and the model(s) can be readily rerun
to generate updated outputs. The initial IMP preparation
costs are a one-time expenditure with periodic minimal
costs to update the IMP over the next 20 to 25 years.
- The vast majority of municipalities are serviced by
an incumbent engineering consultant to some degree. However,
not all consultants offer IMP preparation as part of
their services; nor are all consultants capable of executing
an IMP for even the smaller municipalities.
- IMPs may be multi-disciplined documents (i.e. water/wastewater
treatment, roads, asset management, etc.) that require
a high level of engineering expertise and experience
to execute properly. The same level of expertise is required
to evaluate and analyze any water or wastewater treatment
system or a transportation network as it takes to design
such systems. The Administrator must select a consultant
whose expertise and resources are commensurate with the
degree of complexity of the assignment.
- The proper execution of an IMP not only involves technical
expertise, but also sound project management and cost
estimating skills.
- The Consulting Engineers of Alberta (CEA) can provide
a skills matrix outlining the services provided by the
various consulting firms registered in Alberta. As the
complexity of the assignments increases, the number of
capable consultants becomes limited. As the level of
complexity and magnitude of the scope of work decreases,
more consulting firms may prove to be suitable for the
simpler IMPs.
- There is no need for a municipality to change from
their incumbent consultant to another consultant to commission
an IMP. Simply determine the scope of work of the IMP
and select a firm best suited to perform the work.
|
|