|
Patrick W. Given, M.Sc., P.Eng.
Associated Engineering
Edmonton, Alberta
Contact: givenp@ae.ca
Dennis Mutti, P.Eng., M.A.Sc.
Acres & Associated Environmental Ltd.
Etobicoke, Ontario
Doug Scott, P.Eng.
City of Thunder Bay, Ontario
Darrell Matson
City of Thunder Bay
Thunder Bay, Ontario
The Ontario Ministry of Health
placed a boil water advisory on the City of Thunder Bay
following detection of a Giardia cyst in the water
supply. The advisory impacted only the portion of the water
system served from Loch Lomond, a pristine lake in a protected
watershed.
Two microfiltration (MF) pilot
plants were tested on the Loch Lomond water supply with
and without chemical coagulation, and on the Citys
second source Lake Superior without chemical
coagulation. Particle challenge testing showed that both
test units could reliably achieve 4-log (99.99%) removal
of 2-15 m size particles. With chemical coagulation,
significant colour removal could also be achieved.
The successful pilot test program
led to the fast-track design and construction of a temporary
MF facility which enabled lifting of the boil water advisory.
Performance of the facility has exceeded expectations. The
facility not only is removing cyst-size particles, but also
some colour constituents to the extent that disinfection
byproducts from chlorination of the filtered water appear
to have been reduced. The equipment supplier now classifies
the membrane treatment facility as an ultrafiltration plant.
Successful experience with the
pilot MF and temporary ultrafiltration facilities has provided
confidence leading to the Citys decision to incorporate
the ultrafiltration equipment in a permanent facility.
The City of Thunder Bay has two
water supply sources Loch Lomond and Lake Superior.
Loch Lomond is located in an elevated, protected watershed.
Water quality is generally excellent in terms of turbidity
(generally about 0.4 NTU); however colour, organics and
corrosivity are concerns. Up to November of 1998, treatment
of this water was limited to disinfection with chlorine
and conditioning with sodium silicate. The minimally treated
water from Loch Lomond was distributed by gravity principally
to the south portion of the city. The other source, Lake
Superior, normally has higher turbidity levels (about 1
NTU but with occasional upward excersions due to storms).
This water is treated at the Bare Point direct filtration
water treatment plant and distributed by pumping principally
to the north portion of the city.
In October, 1997, a Boil Water
Advisory was issued by the Medical Officer of Health in
response to detection of a Giardia Lamblia cyst in
the south distribution system. The south distribution system
serves about 40,000 persons, or about 40% of the Citys
total population.
By coincidence microfiltration
(MF) pilot plant trials, under the direction of Acres &
Associated (A&A) Environmental Ltd., were already in
progress when the boil water advisory was issued. MF pilot
testing of Loch Lomond water was conducted from August to
November 1997. Successful performance of the MF trials led
to the consideration of this technology as one of several
alternative means of expediting removal of the Boil Water
Advisory. MF was selected as the preferred alternative in
early 1998 leading to the tendering and commissioning of
temporary MF facilities by November of the same year. The
decision to implement temporary microfiltration of the Loch
Lomond source was based largely on the recognized capabilities
of microfiltration to remove cyst-size particles, as well
as the relative speed at which temporary microfiltration
facilities could be commissioned.
In this paper, we will briefly
review the concepts of MF technology, MF pilot plant test
results, temporary MF facility performance, and plans for
transferring the temporary MF facilities at Loch Lomond
to a permanent location at the Bare Point Water Treatment
Plant.
Microfiltration is one of several
membrane filtration processes. Membranes are thin films
of synthetic organic or inorganic materials which can selectively
separate constituents from a fluid. Fig. 1 illustrates four
common membrane processes and their effective treatment
capabilities.
Transmembrane pressures range
from 1 to 3 atmospheres for microfiltration up to 30 to
150 atmospheres for reverse osmosis. Also with respect to
microfiltration, one manufacturer utilizes vacuum instead
of pressure as the driving force.
Test Equipment
Memcor (Memtec Group) and Zenon
Environmental Inc. provided pilot plant facilities. The
Memcor plant, rated at 85.5 L/min, was utilized throughout
the test program. Zenon supplied a 26.5 L/min pilot plant
which was tested on the Loch Lomond water supply, and a
38 L/min pilot plant which was tested on the Lake Superior
water supply and in particle challenge testing.
Aside from proprietary differences
in the membrane materials, other noted differences between
the two systems were as follows:
Memcor
Zenon
Transmembrane pressure/vacuum Pressure
to 150 kPa Vacuum to 60 kPa
Filtration direction Inside
to outside Outside to inside
Membrane housing Pressure
housing Aerated tank
Regular cleaning Back
pulse air Back pulse chlorinated water
Off-line cleaning (in place) Caustic Chlorine
or citric acid
Test Program
Pilot plant performance test
results presented in this paper refer to Unit 1 (Memcor)
and Unit 2 (Zenon).
Microfiltration pilot testing
began at the Loch Lomond site near the beginning of August
1997 and ended mid-November 1997. Testing at the Bare point
site started mid-November 1997 and ended mid-February 1998.
A&A prepared the test work plan, the plant suppliers
provided initial hands-on training, and the City provided
daily plant operation. Plant operation included record keeping,
adjustments and collection of water samples for analysis.
Raw and treated water samples
were analyzed for particle counts, turbidity, colour, and
other parameters. Only the listed parameters are reviewed
in any detail in this paper.
Pilot Plant Performance
Table 1 illustrates the particle
removal efficiencies of the two MF pilot plant units during
short-term particle challenge testing. Backwash water from
the Bare Point Water Treatment Plant on Lake Superior was
utilized as the feedwater. Raw water particle counts in
the 2-15 micron size range totaled 1.54x106 per
mL. The associated raw water turbidity exceeded 2000 NTU.
Both test units demonstrated the capability to remove at
least 4-log (99.99%) of the particles 90% of the time. Apparent
differences between the two units in the particle log-removal
results are not necessarily significant since testing was
short term. Filtered water turbidities were less than 0.1
NTU.
Table 1.
Particle challenge test results
| |
Log Removals
2-15 m Particles
|
| |
Unit 1
|
Unit 2
|
|
10th Percentile
|
4.0
|
4.3
|
|
Median
|
4.7
|
5.5
|
|
90th Percentile
|
5.1
|
6.1
|
Table 2 summarizes the turbidity
and colour performance data for the two MF pilot plants
operating under three test conditions -- Loch Lomond source
with no chemical pretreatment, Loch Lomond source with chemical
pretreatment, and Lake Superior source (Bare Point) with
no chemical pretreatment. Chemical treatment trials at Loch
Lomond utilized polyaluminum chloride for Unit 1 and alum
for Unit 2.
Table 2. Microfiltration pilot
test summary for turbidity and colour
| |
|
Turbidity, NTU
|
|
Colour, TCU
|
| |
Source -
Treatment |
10th
%*
|
Median
|
90th
%*
|
|
10th
%*
|
Median
|
90th
%*
|
|
Loch Lomond - No Pretreatment
|
| |
Raw Water
|
0.27 |
0.38 |
0.54 |
|
12 |
15 |
22 |
| |
Unit 1 Filtered Water
|
ND |
0.03 |
0.14 |
|
12 |
14 |
21 |
| |
Unit 2 Filtered Water
|
ND |
0.06 |
0.19 |
|
9 |
14 |
23 |
|
Loch Lomond - Pretreatment**
|
| |
Raw Water
|
0.22 |
0.27 |
0.34 |
|
12 |
14 |
15 |
| |
Unit 1 Filtered Water
|
0.01 |
0.03 |
0.08 |
|
1 |
4 |
9 |
| |
Unit 2 Filtered Water
|
0.01 |
0.02 |
0.05 |
|
1 |
1 |
1 |
|
Bare Point - No Pretreatment
|
|
|
|
|
|
|
|
| |
Raw Water
|
0.27 |
1.00 |
1.42 |
|
3 |
4 |
5 |
| |
Unit 1 Filtered Water
|
0.01 |
0.01 |
0.04 |
|
1 |
1 |
2 |
| |
Unit 2 Filtered Water
|
0.01 |
0.01 |
0.06 |
|
1 |
1 |
2 |
* 10th % and 90th
% refer to 10th percentile and 90th
percentiles, respectively.
** Polyaluminum chloride with
Unit 1 and alum with Unit 2.
Both raw water sources exhibited
low turbidity levels: median less than 0.4 NTU for Loch
Lomond and 1.0 NTU for Bare Point. Treated water turbidity
was generally excellent. The 90th percentile
filtered water turbidities for both units were between 0.1
and 0.2 NTU when treating Loch Lomond water without chemical
pretreatment. Under the other two test conditions, 90th
percentile filtered water turbidities were less than 0.1
NTU.
With respect to raw water colour,
the Loch Lomond source showed moderate levels with a median
colour around 15 TCU. The Lake Superior source was significantly
lower at 4 TCU. Therefore, chemical pretreatment trials
to enhance colour removal were not undertaken for the latter
source. Colour and related dissolved organic carbon (DOC)
are parameters not expected to be significantly removed
using microfiltration since the contributing constituents
have minute particle sizes, less than the MF 0.2 m
nominal membrane pore size. Not only are moderate to high
levels of colour a possible aesthetic concern, but they
could also be a health concern if subsequent chlorination
processes lead to excessive formation of chlorinated organic
compounds which are suspected carcinogens. Tests without
chemical pretreatment confirmed that the MF units did not
remove colour and DOC effectively without chemical pretreatment.
However, with such pretreatment at Loch Lomond, significant
removal of colour and DOC was achieved by both test units.
Chemical cleanings were required
for both units at about four week intervals to restore transmembrane
pressures/vacuums to their original values.
Pretendering of microfiltration
equipment was undertaken in February 1998 with tender award
to Zenon in April of that year. The tender was based on
the supply of packaged microfiltration equipment providing
a capacity of 30 ML/d at <2 oC. The tender
documents included a buy-back clause in the event that the
City of Thunder Bay chose not to incorporate the temporary
facilities in a permanent structure. Zenons proposal
incorporated the use of seaway containers for the tanks
with no building except to house blowers, pumps and controls.
Engineering work on the microfiltration installation contract
commenced in May 1998. The completed facilities were operational
and running at maximum design capacity on November 8, 1998.
The total installed cost of the MF facilities was approximately
$6 million.
The City of Thunder Bay has collected
various performance data for the temporary MF facilities
including the main parameters of focus in this paper: particle
counts, turbidity and colour . On-line particle counters
appear to be showing extremely low and consistent filtered
water particle counts. The apparent excellent results will
be undergoing checking in the near future and therefore
will not be reported at this time. Checking of the particle
counters is underway. In addition, the current turbidimeters
consistently register "0" as they are incapable of measuring
turbidities less than 0.1 NTU. Therefore, our discussion
of performance data will be limited to observations of colour
removal.
Figure 2 plots colour measurements
taken by Thunder Bay staff from August to October 1998 (prior
to microfiltration), and from November 1998 to June 1999
(following microfiltration). The results show significant
improvement in filtered water colour during the first month
of MF operation. Subsequently, colour removal reduced somewhat
but generally appeared to remain slightly better than observed
during the pre-MF period. It should be noted that some of
the observed colour removal likely is due to chlorine oxidation
of residual organics in the water. Based on pilot plant
test results, improved colour removal was not expected.
The plant supplier subsequently re-classified the facility
as an ultrafiltration plant.
In addition to the colour data
reported by the City, some laboratory test results from
the Ontario Ministry of Environment & Energy (OMEE)
were available for analysis. Table 3 summarizes data provided
by the City of Thunder Bay for the pre-MF and post-MF periods.
Summarized results for raw and treated Loch Lomond water
include turbidity, colour, dissolved organic carbon, total
trihalomethanes (THMs), and total haloacetic acids (HAAs).
The data show excellent filtered water quality in terms
of turbidity was provided by the MF plant on the sampling
dates shown in Table 3. Also, the data appear to show improved
colour removal is provided by the membrane filtration plant,
helping to support Zenons statement that the plant
should be classified as an ultrafiltration facility. Although
limited sample tests show dissolved organic carbon removals
appeared minor, the levels of THMs and HAAs appear improved
(reduced from >100 g/L to <100 g/L). Additional
testing will be required to determine if these apparent
improvements continue in future.
The Loch Lomond membrane treatment
plant is manned 8 hours per day and is monitored via PLC
from the Bare Point plant during the remaining periods.
During normal plant operation, the membranes are automatically
back pulsed every 20 minutes for a 30 second duration. Off-line
membrane cleaning has been required approximately at six
week intervals during winter operation and up to five months
during summer operation. Sodium hypochlorite solution is
used for cleaning the membranes by soaking them up to eight
hours, followed by dechlorination and a rinse cycle before
returning the units to service. To date, citric acid has
not been required for cleaning.
Table 3. OMEE test results
before and after "microfiltration"
| |
Before "Microfiltration"
|
After "Microfiltration"
|
|
Parameter
|
Jan 1/98
|
Sep 28/98
|
May 25/99
|
| |
Raw
|
Treated
|
Raw
|
Treated
|
Raw
|
Treated
|
|
Turbidity, FTU
|
0.42
|
0.22
|
0.40
|
0.78
|
0.32
|
0.08
|
|
Colour, TCU
|
13.6
|
6.2
|
9.4
|
4.2
|
69.6*
|
5.2
|
|
DOC, mg/L
|
5.1
|
5.1
|
5.0
|
5.1
|
5.1
|
4.6
|
|
Total THMs, g/L
|
<0.5
|
125
|
<0.5
|
132
|
<0.5
|
66.5
|
|
Total HAAs, g/L
|
<0.5
|
113
|
<0.5
|
160
|
<0.5
|
77.4
|
* The raw water colour on
May 25th requires confirmation. Independent testing
by Thunder Bay operators showed colour readings in the 10
to 20 range during that time period.
The City of Thunder Bay is proceeding
with plans to convert the City's water supply to a single
source at the Bare Point Water Treatment Plant on Lake Superior.
The plant will also be upgraded to achieve 4-log removal
and/or inactivation of Cryptosporidium and Giardia
cysts. Evaluated major technologies to meet this treatment
goal included ultrafiltration membranes and direct filtration
with ultraviolet (UV) or ozone disinfection. Since the City
already has temporary ultrafiltration (UF) facilities in
place at the Loch Lomond location, the application of UF
technology at the permanent location became more economically
feasible. The current recommendation calls for:
- the addition of one filter and associated
facilities to expand the existing Bare Point direct
filtration capacity from 63 ML/d to 84 ML/d,
- provision of UV irradiation for the existing
and new direct filtration treated water, and
- relocation of the existing ultrafiltration
units from the temporary facility to the permanent facility
at Bare Point to provide an additional capacity of 38
ML/d.
The capacity of the microfiltration
facilities was originally rated at 30 ML/d but is being
re-rated and guaranteed by the supplier at 38 ML/d. The
expanded and upgraded facilities will have and an overall
capacity of 122 ML/d. Of course, secondary disinfection
with chlorine will remain.
The main conclusions in this
paper are summarized as follows:
- Particle challenge testing of two pilot
plants showed that microfiltration achieved at least
a 4-log reduction of 2-15 m size particles over
90% of the time;
- pilot testing without chemical pretreatment
showed that the microfiltration equipment consistently
(90% of the time) achieved a filtered water turbidity
less than 0.1 NTU for the Lake Superior source and less
than 0.2 NTU for the Loch Lomond source;
- chemical coagulation greatly assisted
in the removal of colour by the pilot microfiltration
units treating Loch Lomond source water;
- the Thunder Bay project demonstrated
that microfiltration or ultrafiltration equipment can
be mobilized quickly to address a water treatment emergency
(boil water advisory);
- operating performance of the temporary
ultrafiltration facilities met and even exceeded expectations;
and
- successful operating experience with
the temporary ultrafiltration facilities has provided
the confidence to proceed with planning for their permanent
incorporation at the Bare Point Water Treatment Plant.
|