The City of Edmonton retained Associated Engineering to complete the bridge condition assessment and preliminary rehabilitation strategy reports for three overpasses at the intersection of 170 Street: B185 over Yellowhead Trail & B170/B171 (NB/SB) over the CN Rail Bissell Yard.
The condition assessments included review of the bridge’s history, detailed visual inspection and materials testing, and load evaluation. The preliminary rehabilitation strategies included the review of controlling factors such as structural condition, roadway alignment and drainage, environmental issues, traffic staging, public engagement with local businesses including CN Rail, and utility coordination.
Client
City of Edmonton
Project Highlights
The rehabilitation works for B170 and B171 were split into two stages. The B171 rehabilitation was completed in the first stage, which began in April 2017 and was completed October 2017. Rehabilitation of B170 was completed during the second stage and began in October 2019 and was completed June 2021.
People on this project
More Transportation Projects
See all projects
Pedestrian Bridges
Hangingstone River Pedestrian Bridge
Transportation
Inuvik Airport Runway 06-24 Extension and Airside Civil Infrastructure Improvements
Transportation
LNG Canada Heavy Haul Bridges
Infrastructure
Baxter Bridge Rehabilitation
Transportation
Sutherland Ave Pedestrian Bridge
Transportation
Glenmore Dam Utility Relocation
Transportation
Pedestrian Bridge 151 Rehabilitation
Transportation
184 Street and Yellowhead Trail Interchange
Transportation
7 Avenue S. Bike Boulevard
Transportation
Calgary Airport Runway and Tunnel
Transportation
Bermuda Runway Rehabilitation
Infrastructure
Highway 69 Twinning
Transportation
Highway 7 Haney Bypass Intersection Improvements
Transportation
Ironworkers Memorial Second Narrows Bridge Fatigue Study
Bridges
Seymour Canyon Suspension Bridge
LEADERSHIP INSIGHTS
See all insights