Built in 1973, the Columbia Street Pump Station is located in Vancouver’s historic Gastown neighbourhood.
Due to operational concerns and capacity constraints, in 2001, the Greater Vancouver Sewerage and Drainage District decided to upgrade the existing facility, and retained Associated Engineering to provide design and contract administration services.
The pump station has an initial design capacity of 455 L/s (three pumps) and an ultimate capacity of 540 L/s (four pumps). Pumps are located in two, self-cleaning, trench-style wet wells. Grit removal chambers are located upstream of the pumps. Variable frequency drives control operation of each of the pumps.

Client
The Greater Vancouver Sewerage and Drainage District

Project Highlights
12.5kV dual
high voltage electrical service
600mm
diameter sanitary sewer
Key considerations during design were the narrow lot, site constraints, and the need to maintain the pump station in service during construction. The architecture of the new facility had to blend in with the heritage neighbourhood. The City also requested educational display panels, canopy for pedestrian shelter, lighting for pedestrian and display areas, and landscaping.
The design included noise and odour mitigation, a new, 12.5 kV dual, high voltage electrical service, and modifications to the 600 mm diameter sanitary sewer.
More Building Structures Projects
See all projects

Infrastructure
Kikendaasogaming Elementary School Deficiency Repairs

Building Structures
26 SW Marine Drive Commercial Development

Building Structures
Bone Yard Operations Centre Office Expansion

Infrastructure
Gitwinksihlkw Water Treatment Plant

Building Structures
Broadview Drive Commercial Development

Building Mechanical
Oakmont Pump Station Upgrades

Building Structures
Elkford Community Centre

Buildings
Stoney Nakoda Child & Family Services Building Assessment

Building Mechanical
Arbutus Water Treatment Plant

Buildings
Wood Innovation and Design Centre

Building Mechanical
Eiling Kramer Campground Park Service Centre

Building Mechanical
Hazardous Materials Survey and Abatement Monitoring of Buildings

Water
Fort Chipewyan Water Treatment Plant Expansion

Building Mechanical
Elijah Smith School Energy Audit

Building Mechanical
Hazardous Materials Survey and Abatement Monitoring
LEADERSHIP INSIGHTS
See all insights