The project was undertaken to improve transportation efficiencies on the Tibbitt to Contwoyto Winter Road (TCWR), while ensuring a high level of safety and no additional risk to winter road operators and drivers.
NOR•EX Engineering provided ice engineering design, ice loading tables, and quality assurance program for improved transportation up the TCWR to resupply three diamond mines north of Yellowknife. The project team provided the ice engineering design and overall quality assurance programs.
The enhancements saved the client 116 fewer truckloads in 2014; achieved a 5% increase in truck payload capacity until the Winter Road was operating at maximum capacity (100% Super B Gross Vehicle Weight); and provided an operational cost savings in excess of $600,000/year moving forward.
Project Highlights
More Transportation Projects
See all projects
Transportation
Edmonton Valley Line – Stage 1
Bridges
Agassiz-Rosedale Bridge – Renewal Options Analysis and Preliminary Rehabilitation Design
Transportation
Bermuda Runway Rehabilitation
Transportation
Don River Blvd. Bridge Rehabilitation
Transportation
Port Mann Highway 1 Improvements Highway, Structural and Drainage Engineering
Bridges
Coast Meridian Bridge
Transportation
Pitt River Bridge
Airports
Vancouver International Airport South Airfield Upgrades
Transportation
Still Creek Pedestrian Bridge Replacement
Transit
SkyTrain Crossing of South Point Drive
Transportation
170th Street Pedestrian Bridge
Streetscaping
Langford Cultural District
Bridges
Moody Street Overpass
Transportation
Bobtail Forest Service Road Overpass
Transportation