Associated provided environmental services for the construction of the Deh Cho Bridge.
Associated Engineering was responsible for overall project management. The unique circumstances, challenges, and large project team demanded a special project management approach, which included:
• Involving all stakeholders from the beginning and keeping them fully engaged throughout. Risks were collectively identified and mitigated, which prevented holdups due to agency requirements.
• Developing a tailor-made, internet-based, project document control system. All official project documents were distributed instantaneously to team members who could access it from anywhere via the internet.
• Developing and maintaining a comprehensive project website, complete with real-time web camera feeds, which kept the public informed of the project’s status.
• Distributing quarterly project newsletters to each household in the Northwest Territories.
• Procuring two professionally built scale models of the bridge for display in prominent locations in the Northwest Territories.


Project Highlights
More Environmental Projects
See all projects

Environmental
Okanagan Valley Drought Planning

Environmental
Port of Vancouver – Climate Change Adaptation

Climate Change Adaptation & Mitigation
Calgary Northwest Inner City Drainage Study

Environmental
McIntyre Dam Fish Passage

Environmental
Great Slave Lake Nutrient Risk Assessment and Treatment Improvement Options Study Fiddlers Lagoon Wastewater Treatment

Environmental
Data System Planning

Environmental
Climate Change Risk Assessment

Environmental
Environmental Screening, Clearance Reporting and Post-Reclamation Construction Monitoring on Line 21

Contaminated Sites Management
Sioux Lookout Phase I Environmental Site Assessment

Soil Bioengineering
Blackmud Creek Erosion Feasibility Study and Design

Environmental
South Cranberry Creek Hydroelectric Facility Long-Term Environmental Monitoring

Containment Systems
Silverberry Secure Landfill

Environmental
Phase I Environmental Site Assessment of 10 Housing Units

Transportation
2021 Flood Recovery – Nicomen Community Bridge Planning Study

Environmental
Phase III ESA and Remedial Action Plan at Fort Providence Ferry Landings and Maintenance Compound
LEADERSHIP INSIGHTS
See all insights