Associated provided environmental services for the construction of the Deh Cho Bridge.
Associated Engineering was responsible for overall project management. The unique circumstances, challenges, and large project team demanded a special project management approach, which included:
• Involving all stakeholders from the beginning and keeping them fully engaged throughout. Risks were collectively identified and mitigated, which prevented holdups due to agency requirements.
• Developing a tailor-made, internet-based, project document control system. All official project documents were distributed instantaneously to team members who could access it from anywhere via the internet.
• Developing and maintaining a comprehensive project website, complete with real-time web camera feeds, which kept the public informed of the project’s status.
• Distributing quarterly project newsletters to each household in the Northwest Territories.
• Procuring two professionally built scale models of the bridge for display in prominent locations in the Northwest Territories.
Project Highlights
More Environmental Projects
See all projects
Fish, Wildlife & Ecosystems
Regional Wildlife Monitoring Plan
Environmental
Data System Planning
Environmental
Big Bend Master Drainage Plan
Environmental
Meadow Valley Groundwater Availability Study
Environmental Assessment
Environmental Assessment of Westside Road
Environmental
Sicamous to Armstrong Rail Trail Agricultural Component
Transportation
Highway 7 Haney Bypass Intersection Improvements
Environmental
Revegetation Manual Revisions
Environmental
Drinking Water System Improvements in Quaaout Community
Environmental
Phase I and II Environmental Site Assessments and Compliance Audit Great Glacier Salmon Plant and Camp
Environmental
Community Lands Engagement Study & Environmental Site Assessment
Contaminated Sites Management
Phase I and II Environmental Site Assessment – Margaret’s Landing Development
Environmental
McIntyre Dam Fish Passage
Sustainable Management
Environmental Management System and Legislative Compliance Assessment
Environmental
Phase III ESA and Remedial Action Plan at Fort Providence Ferry Landings and Maintenance Compound