The client undertook a large blasting and hauling operation as part of the infrastructure improvements supporting the Slater River Project.
NOR•EX Engineering provided safety services, ice engineering, and a road management plan for an ice crossing over the Mackenzie River, south of Norman Wells, Northwest Territories.
The client transported approximately 65-70 loads per day across the Mackenzie River, for close to 60 days, for an overall haul total of 130,000 tonnes. The program recorded zero ice related incidents during the season. The services provided improved efficiencies and cost savings for the client’s hauling program within a strong safety environment.

Client
NOR•EX Engineering

Project Highlights
65-70
transported loads per day
130,000t
for 60 days
More Infrastructure Projects
See all projects

Transportation
Glenmore Dam Utility Relocation

Infrastructure
Howard’s Pass Access Road Bridge Replacement and Road Improvement

Water
Fort Chipewyan Water Treatment Plant Expansion

Airports
Christina Lake Infrastructure Upgrading

Environmental
Calgary Zoo Flood Mitigation

Transportation
St. Andrews Lock and Dam Comprehensive Detailed Inspection

Environmental
Sicamous to Armstrong Rail Trail Agricultural Component

Infrastructure
East Brampton Trunk Sanitary Sewer Twinning

Infrastructure
Saskatoon South East Water Supply System Canal Rehabilitation

Energy
District Energy – Blatchford Redevelopment

Transportation
184 Street and Yellowhead Trail Interchange

Transportation
Mission Bridge Seismic Retrofit

Climate Change Adaptation & Mitigation
Calgary Northwest Inner City Drainage Study

Infrastructure
North Interceptor Sanitary Trunk

Energy
Site C Clean Energy
LEADERSHIP INSIGHTS
See all insights