Location
Norman Wells, NWT
Expertise
Infrastructure
Ice Engineering
Share
The client undertook a large blasting and hauling operation as part of the infrastructure improvements supporting the Slater River Project.
NOR•EX Engineering provided safety services, ice engineering, and a road management plan for an ice crossing over the Mackenzie River, south of Norman Wells, Northwest Territories.
The client transported approximately 65-70 loads per day across the Mackenzie River, for close to 60 days, for an overall haul total of 130,000 tonnes. The program recorded zero ice related incidents during the season. The services provided improved efficiencies and cost savings for the client’s hauling program within a strong safety environment.
Client
NOR•EX Engineering
Project Highlights
65-70
transported loads per day
130,000t
for 60 days
More Infrastructure Projects
See all projects
Land Development
Lethbridge Crossings Development
Transportation
Overlea Blvd. Bridge Rehabilitation
Buildings
Riel Recreation Park Redevelopment
Environmental
Phase I Environmental Site Assessment of 10 Housing Units
Building Structures
Bone Yard Operations Centre Office Expansion
Infrastructure
Irrigation Sustainability and Water Balance Seepage Assessment Study
Streetscaping
Vanalman Avenue Upgrades
Building Mechanical
South Arm District Energy Utility Phase 1 Technical Feasibility Study
Infrastructure
Drainage Improvement Study
Infrastructure
Burnaby Lake Rowing Club Pavilion Floating Dock
Infrastructure
Oakville Fourth Line Closed Landfill
Infrastructure
Medicine Hat Sidewalk Inventory and Asset Management Program
Transportation
Still Creek Pedestrian Bridge Replacement
Streetscaping
Nigel Valley Public Spaces
Land Development