Associated Engineering was contracted to provide engineering services for the Emergency Flood Damage Reduction Program.
Due to high amounts of rain through May, June and July properties and communities were in risk of flooding. Emergency drainage improvements were designed and implemented, along with long term solutions in some instances.
Associated Engineering was requested to provide technical assistance and site inspections for the nine separate locations. Reports were prepared for the Water Security Agency to outline emergency flood relief measures and site investigations including major construction. These mitigation measures were needed immediately, and could be altered to be long term.
Project Highlights
More Climate Change Adaptation & Mitigation Projects
See all projects
Climate Change Adaptation & Mitigation
Livingston Trail Environmental Control Facility
Environmental
Growth and Economic Development Strategy
Climate Change Adaptation & Mitigation
Climate Change Adaptation Scenario Development and Vulnerability and Risk Assessment
Climate Change Adaptation & Mitigation
Highway 40 Emergency Flood Reconstruction
Climate Change Adaptation & Mitigation
RISC Hydrometric Standards Review
Environmental
Big Bend Master Drainage Plan
Climate Change Adaptation & Mitigation
Fraser River Foreshore – Reach 9 Dyke
Environmental
John Matthews Creek Ravine Management Strategy and Creek Restoration
Buildings
Climate Change Risk Assessment for Buildings
Climate Change Adaptation & Mitigation
Nanaimo Reservoir No. 1 and Energy Recovery Facility
Environmental
Okanagan Valley Drought Planning
Climate Change Adaptation & Mitigation
Calgary Zoo Flood Mitigation
Environmental
Climate Change Risk Assessment
Climate Change Adaptation & Mitigation
Toronto Water Quality Master Plan
Transportation